Wind energyDecisionClare
Clare County Council refuses permission for 4-turbine wind farm with 150m turbines at Kilrush, Co. Clare
23 May 2024 · Permission.ie Planning Wire · from the Clare County Council planning register · published 1 September 2026
Clare County Council refused permission on 23 May 2024 for a 4-turbine wind farm with 150m turbines at Kilrush, an application first lodged on 29 March 2024.
Key facts
- Reference
- 2460143
- Planning authority
- Clare County Council
- Location
- Ballykett Tullabrack East Tullabrack West Tullabrack and Gower South, Kilrush, Co. Clare
- Received
- 29 March 2024
- Application type
- PERMISSION
- Site area
- 31.1 hectares
- Turbines
- 4
- Turbine height
- 150 m
- Operational life
- 35 years
- Status
- APPLICATION FINALISED
- Decision
- REFUSED
- Decision date
- 23 May 2024
- Appeal
- ABP-319961-24 · CONDITIONAL
- Council file
- View on the Clare County Council planning portal
In context
It is one of 4 wind energy applications Clare County Council has received in the past twelve months, against 61 nationally. Of the 84 such applications decided by councils in the past three years, 74% were granted.
What happens next
The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 23 May 2024. If no appeal is lodged, the council’s decision stands and a final grant issues.
The development description, as lodged
Verbatim from the Clare County Council register. This is the source for every figure in the story above.
for the erection of 4 no. wind turbines with an overall ground to blade tip height of 150m with a rotor diameter of 136m and a hub height of 82m, the construction of crane hardstand areas and turbine foundations, the creation of a new site entrance onto the L6132, construction of 1 no. temporary construction compound with associated temporary site offices, parking areas and security fencing, installation of 1 no. permanent meteorological mast of 82m overall height, construction of new internal site access tracks and upgrade of existing site track, to include all associated drainage including new clear span bridge crossing of the Moyasta River, development of a site drainage network, biodiversity enhancement measures, construction of 1 no. permanent 38kV electrical substation, 2 no. permanent spoil storage areas, all associated underground electrical and communications cabling connecting the wind turbines to the wind farm substation and to the existing Tullabrack 110kV Substation, all ancillary forestry felling to facilitate construction including the development of one no. borrow pit, vertical realignment of an existing crest curve on the L6132. This application is seeking a ten year permission and a 35 year operational life from the date of commissioning of the wind farm. The planning application is accompanied by an Environmental Impact Assessment (EIAR) and a Natura Impact Statement (NIS)
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "Clare County Council refuses permission for 4-turbine wind farm with 150m turbines at Kilrush, Co. Clare", 23 May 2024. https://www.permission.ie/news/clare-county-council/2460143
<p>Source: <a href="https://www.permission.ie/news/clare-county-council/2460143">Clare County Council refuses permission for 4-turbine wind farm with 150m turbines at Kilrush, Co. Clare</a>, Permission.ie analysis of the national planning register, 23 May 2024.</p>
Map, site boundary, timeline and nearby applications for 2460143.
All wind energy applicationsThe full register view, with a map and decision statistics.
Get stories like this the day they are lodged
A county watch emails you every new application in Clare the week it appears.
Set up alerts