Clare County Council grants permission for 99.2-hectare solar farm at Manusmore, Clarecastle, Co. Clare
3 November 2025 · Permission.ie Planning Wire · from the Clare County Council planning register · published 1 September 2026
Clare County Council granted permission on 3 November 2025 for a 99.2-hectare solar farm at Manusmore, Clarecastle, an application first lodged on 9 September 2025.
Key facts
- Reference
- 25291
- Planning authority
- Clare County Council
- Location
- Manusmore, Clarecastle, Co. Clare
- Received
- 9 September 2025
- Application type
- EXTENSION OF DURATION
- Site area
- 99.2 hectares
- Status
- APPLICATION FINALISED
- Decision
- UNCONDITIONAL
- Decision date
- 3 November 2025
- Council file
- View on the Clare County Council planning portal
In context
It is one of 9 solar farm applications Clare County Council has received in the past twelve months, against 335 nationally. Of the 573 such applications decided by councils in the past three years, 92% were granted.
What happens next
The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 3 November 2025. If no appeal is lodged, the council’s decision stands and a final grant issues.
The development description, as lodged
Verbatim from the Clare County Council register. This is the source for every figure in the story above.
to Extend the Appropriate Period of Planning permission for P20/562 the development will consist of a planning permission for a period of 5 years to construct and complete a Solar PV Energy development with a total site area of 99.2 hectares, to include a single storey electrical substation building, electrical transformer and invertor station modules, solar PV panels ground mounted on support structures, internal access tracks, security fencing, electrical cabling and ducting, CCTV and other ancillary infrastructure, drainage, additional landscaping and habitat enhancement as required and associated site development works including works relating to the access to the site. The Solar farm will be operational for 35 years. A Natura Impact Statement has been prepared in respect of this planning application
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "Clare County Council grants permission for 99.2-hectare solar farm at Manusmore, Clarecastle, Co. Clare", 3 November 2025. https://www.permission.ie/news/clare-county-council/25291
<p>Source: <a href="https://www.permission.ie/news/clare-county-council/25291">Clare County Council grants permission for 99.2-hectare solar farm at Manusmore, Clarecastle, Co. Clare</a>, Permission.ie analysis of the national planning register, 3 November 2025.</p>
Map, site boundary, timeline and nearby applications for 25291.
All solar farms applicationsThe full register view, with a map and decision statistics.
Get stories like this the day they are lodged
A county watch emails you every new application in Clare the week it appears.
Set up alerts