Wind energyDecisionClare

Clare County Council refuses permission for 5-turbine wind farm with 150m turbines at Tooreen, Slievenalicka Illaunbaun, Co. Clare

4 December 2025 · Permission.ie Planning Wire · from the Clare County Council planning register · published 1 September 2026

Clare County Council refused permission on 4 December 2025 for a 5-turbine wind farm with 150m turbines at Tooreen, Slievenalicka Illaunbaun, an application first lodged on 27 August 2025.

Key facts

Reference
2560520
Planning authority
Clare County Council
Location
Tooreen, Slievenalicka Illaunbaun, Drumbaun and Lackamore Co Clare
Received
27 August 2025
Application type
PERMISSION
Site area
37.6 hectares
Turbines
5
Turbine height
150 m
Permission sought
10 years
Operational life
35 years
Status
APPEALED
Decision
REFUSED
Decision date
4 December 2025
Appeal
PL-500605-CE-26

In context

It is one of 4 wind energy applications Clare County Council has received in the past twelve months, against 61 nationally. Of the 85 such applications decided by councils in the past three years, 74% were granted.

What happens next

The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 4 December 2025. If no appeal is lodged, the council’s decision stands and a final grant issues. The applicant sought a 10-year permission, which sets how long they have to start the development.

The development description, as lodged

Verbatim from the Clare County Council register. This is the source for every figure in the story above.

for the development of Illaunbaun Wind Farm in the townlands of Tooreen, Slievenalicka, Illaunbaun, Drumbaun & Lackamore (although no infrastructure will be sited within Lackamore townland), County Clare. The development will consist of: • Construction of 5 wind turbines with a maximum overall blade tip height of 150 m. • Construction of associated turbine foundations, crane pad hardstand and assembly areas. • Construction of one permanent 38 kV electrical on-site substation with one control building with welfare facilities, all associated electrical switchgear, security fencing, underground cabling, drainage infrastructure, and all ancillary works. • All associated internal underground electrical and communications cabling connecting the wind turbines to the on-site Substation. • Upgrade of existing tracks, roads and provision of new site access roads to facilitate construction & operation of the wind farm. • Two borrow pits. • Three peat repository areas for peat & spoil management. • Construction of one temporary construction compound. • Development of internal site drainage. • Permanent & Temporary tree felling to accommodate the construction & operation. • Signages and • All associated site development works. This application is seeking 10-year planning permission, along with a 35-year operational life for the wind farm from the date of its commissioning. The development is covered by the provisions of the Renewable Energy Directive III (Directive 2023/2413) Yes x No The planning application is subject to section 34D of the Planning and Development Act, 2000, as amended. When a notice is issued in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply. An Environmental Impact Assessment Report (EIAR) & Screening for Appropriate Assessment have been prepared in respect of the planning application and will be submitted to the planning authority with the application.

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "Clare County Council refuses permission for 5-turbine wind farm with 150m turbines at Tooreen, Slievenalicka Illaunbaun, Co. Clare", 4 December 2025. https://www.permission.ie/news/clare-county-council/2560520

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/clare-county-council/2560520">Clare County Council refuses permission for 5-turbine wind farm with 150m turbines at Tooreen, Slievenalicka Illaunbaun, Co. Clare</a>, Permission.ie analysis of the national planning register, 4 December 2025.</p>
Full application record

Map, site boundary, timeline and nearby applications for 2560520.

All wind energy applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Clare the week it appears.

Set up alerts