Wind energyDecisionClare
Clare County Council refuses permission for single-turbine wind farm with 150m turbines at Slievenalicka, Illaunbaun Drumbaun, Co. Clare
15 December 2025 · Permission.ie Planning Wire · from the Clare County Council planning register · published 1 September 2026
Clare County Council refused permission on 15 December 2025 for a single-turbine wind farm with 150m turbines at Slievenalicka, Illaunbaun Drumbaun, an application first lodged on 19 September 2025.
Key facts
- Reference
- 2560578
- Planning authority
- Clare County Council
- Location
- Slievenalicka, Illaunbaun Drumbaun, and Lackamore
- Received
- 19 September 2025
- Application type
- PERMISSION
- Site area
- 23.1 hectares
- Turbines
- 1
- Turbine height
- 150 m
- Permission sought
- 10 years
- Operational life
- 35 years
- Status
- APPLICATION FINALISED
- Decision
- REFUSED
- Decision date
- 15 December 2025
- Council file
- View on the Clare County Council planning portal
In context
It is one of 4 wind energy applications Clare County Council has received in the past twelve months, against 61 nationally. Of the 85 such applications decided by councils in the past three years, 74% were granted.
What happens next
The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 15 December 2025. If no appeal is lodged, the council’s decision stands and a final grant issues. The applicant sought a 10-year permission, which sets how long they have to start the development.
The development description, as lodged
Verbatim from the Clare County Council register. This is the source for every figure in the story above.
for the development at this site in the townlands of Slievenalicka, Illaunbaun, Drumbaun and Lackamore (although no infrastructure will be sited within Lackamore townland), Co. Clare. The development will consist of: • Construction of 1 wind turbine with a maximum overall blade tip height of 150m. • Construction of associated turbine foundation, crane pad hardstand and assembly area. • Construction of one permanent 38 kV electrical on-site substation with one control building with welfare facilities, all associated electrical switchgear, security fencing, underground cabling, drainage infrastructure, and all ancillary works. • All associated internal underground electrical and communications cabling connecting the wind turbine to the on-site Substation. • Upgrade of existing tracks, roads and provision of new site access roads to facilitate construction and operation of the turbine. • Two borrow pits. • One peat repository area for peat and spoil management. • Construction of one temporary construction compound. • Development of internal site drainage. • Permanent and Temporary tree felling to accommodate the construction and operation of the turbine. • Signages. • All associated site development works. This application is seeking a 10-year planning permission, together with a 35-year operational life for the wind turbine from the date of its commissioning. The development is covered by the provisions of the Renewable Energy Directive III (Directive 2023/2413) Yes. The planning application is subject to section 34D of the Planning and Development Act, 2000, as amended. When a notice is issued in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply. An Environmental Impact Assessment Report (EIAR) and Screening for Appropriate Assessment have been prepared in respect of the planning application and will be submitted to the Planning Authority with the application
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "Clare County Council refuses permission for single-turbine wind farm with 150m turbines at Slievenalicka, Illaunbaun Drumbaun, Co. Clare", 15 December 2025. https://www.permission.ie/news/clare-county-council/2560578
<p>Source: <a href="https://www.permission.ie/news/clare-county-council/2560578">Clare County Council refuses permission for single-turbine wind farm with 150m turbines at Slievenalicka, Illaunbaun Drumbaun, Co. Clare</a>, Permission.ie analysis of the national planning register, 15 December 2025.</p>
Map, site boundary, timeline and nearby applications for 2560578.
All wind energy applicationsThe full register view, with a map and decision statistics.