Solar farmsLodgedClare
11.9-hectare solar farm proposed at in the, of Ballymorris, Co. Clare
25 November 2026 · Permission.ie Planning Wire · from the Clare County Council planning register
Ballymorris Solar Farm Limited lodged plans with Clare County Council on 25 November 2026 for an 11.9-hectare solar farm at in the, of Ballymorris. The application seeks a 10-year permission. Submissions from the public can be made until 7 January 2027, and a decision is due by 28 January 2027.
Live from the council register. This application was read from Clare County Council’s own register the day it was listed. It has not yet reached the national planning dataset, which runs one to five weeks behind; the full record page, map and site boundary will appear here when it does.
Key facts
- Reference
- 2660787
- Planning authority
- Clare County Council
- Location
- in the townland, of Ballymorris,, Co. Clare
- Applicant
- Ballymorris Solar Farm Limited
- Received
- 25 November 2026
- Site area
- 11.9 hectares
- Permission sought
- 10 years
- Status
- PRE-VALIDATION
- Decision due
- 28 January 2027
- Submissions until
- 7 January 2027
- Council file
- View on the Clare County Council planning portal
In context
It is one of 7 solar farm applications Clare County Council has received in the past twelve months, against 348 nationally. Of the 595 such applications decided by councils in the past three years, 92% were granted.
What happens next
Anyone can make a submission or observation to Clare County Council until 7 January 2027, for a fee of €20. Only those who make a submission can later appeal the decision. The council is due to decide by 28 January 2027, unless it requests further information, which stops the clock.
The development description, as lodged
Verbatim from the Clare County Council register. This is the source for every figure in the story above.
a 10 Year Planning Permission. A solar farm and part overground / part underground cabling grid connection to Ballymorris 38kV substation with a total area of circa 11.9 hectares. The solar farm will consist of solar panels on ground mounted frames, 2 no. single storey electrical inverter/transformer stations, 1 no. single storey spare parts container, 2 no. battery energy storage containers, 1 no. Medium Voltage (MV) Substation (comprising either single-storey building or 2 no. modular units), 1 no. weather station, underground electrical ducting and cabling within the development site, security fencing, CCTV, access tracks, 4 no. drain crossings, temporary construction compound, landscaping and all associated ancillary development and drainage works. Construction and operational access will be via 1 no. new entrance from the L7124 local road. The proposed development will include overhead MV electricity line and underground electrical ducting and cabling within the solar farm development site and within the L7124 and L3118 public roads to Ballymorris 38kV substation to the east. The operational lifespan of the solar farm will be 40 years and planning permission is requested for this duration. This planning application relates to a proposed solar farm on lands where planning permission currently exists for a solar farm, Clare County Council Reference 16368 / An Coimisiún Pleanála Reference PL03.247632 refers. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply.
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "11.9-hectare solar farm proposed at in the, of Ballymorris, Co. Clare", 25 November 2026. https://www.permission.ie/news/clare-county-council/2660787
<p>Source: <a href="https://www.permission.ie/news/clare-county-council/2660787">11.9-hectare solar farm proposed at in the, of Ballymorris, Co. Clare</a>, Permission.ie analysis of the national planning register, 25 November 2026.</p>
The Clare County Council record for 2660787, with documents and drawings as lodged.
All solar farms applicationsThe full register view, with a map and decision statistics.
Get stories like this the day they are lodged
A county watch emails you every new application in Clare the week it appears.
Set up alerts