Cork County Council grants permission for 3.8-hectare solar farm at Ballybeg and Turbeagh Mitchelstown, Co. Cork
14 January 2025 · Permission.ie Planning Wire · from the Cork County Council planning register · published 31 August 2026
Cork County Council granted permission on 14 January 2025 for a 3.8-hectare solar farm at Ballybeg and Turbeagh Mitchelstown, an application first lodged by is seeking a 10-year planning permission and an operational period of 40 years on 28 June 2024.
Key facts
- Reference
- 24/5212
- Planning authority
- Cork County Council
- Location
- Ballybeg and Turbeagh Mitchelstown Co. Cork
- Applicant
- is seeking a 10-year planning permission and an operational period of 40 years
- Received
- 28 June 2024
- Application type
- PERMISSION
- Site area
- 3.8 hectares
- Permission sought
- 10 years
- Operational life
- 40 years
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision date
- 14 January 2025
- Council file
- View on the Cork County Council planning portal
In context
It is one of 52 solar farm applications Cork County Council has received in the past twelve months, against 333 nationally. Of the 572 such applications decided by councils in the past three years, 92% were granted.
What happens next
The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 14 January 2025. If no appeal is lodged, the council’s decision stands and a final grant issues. The applicant sought a 10-year permission, which sets how long they have to start the development.
The development description, as lodged
Verbatim from the Cork County Council register. This is the source for every figure in the story above.
Permission for a photovoltaic (Solar PV) energy generation scheme with a total area of 3.76ha within the townlands of Ballybeg and Turbeagh in Mitchelstown Co. Cork. The development will consist of the installation of 4,182 no. ground mounted Solar PV arrays, a 20kV substation, the installation of 120m of 20kV underground electrical cabling from the proposed substation to an existing pole and overhead line to connect to the national grid, the upgrade of an existing entrance off the local road to serve as a permanent site entrance for the solar farm and all associated site development works including upgrading 80m of existing tracks and installing 435m of new access track 3m wide and all associated site works. The applicant is seeking a 10-year planning permission and an operational period of 40 years.
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "Cork County Council grants permission for 3.8-hectare solar farm at Ballybeg and Turbeagh Mitchelstown, Co. Cork", 14 January 2025. https://www.permission.ie/news/cork-county-council/24%2F5212
<p>Source: <a href="https://www.permission.ie/news/cork-county-council/24%2F5212">Cork County Council grants permission for 3.8-hectare solar farm at Ballybeg and Turbeagh Mitchelstown, Co. Cork</a>, Permission.ie analysis of the national planning register, 14 January 2025.</p>
Map, site boundary, timeline and nearby applications for 24/5212.
All solar farms applicationsThe full register view, with a map and decision statistics.
Get stories like this the day they are lodged
A county watch emails you every new application in Cork the week it appears.
Set up alerts