An applicant lodged plans with Cork County Council on 26 November 2024 for a 52-turbine wind farm with 91m turbines at Gneeves Millstreet Co.Cork. A decision is due by 29 January 2025.
Key facts
- Reference
- 24/6238
- Planning authority
- Cork County Council
- Location
- Gneeves Millstreet Co.Cork
- Received
- 26 November 2024
- Application type
- PERMISSION
- Site area
- 10.1 hectares
- Turbines
- 52
- Turbine height
- 91 m
- Status
- INCOMPLETED APPLICATION
- Decision due
- 29 January 2025
- Submissions until
- 8 January 2025 (closed)
- Council file
- View on the Cork County Council planning portal
In context
It is one of 8 wind energy applications Cork County Council has received in the past twelve months, against 61 nationally. Of the 85 such applications decided by councils in the past three years, 74% were granted.
What happens next
The five-week window for public submissions has closed. The council is due to decide by 29 January 2025, unless it requests further information, which stops the clock.
The development description, as lodged
Verbatim from the Cork County Council register. This is the source for every figure in the story above.
A fifteen (15) year planning permission for continuation of the operational life of the existing Gneeves wind farm from the date of expiration (November 2025) of the current planning permission (N/99/616, 03/6585, 04/188). The site measures 10.101 hectares. The existing wind farm consists of the following; 11 no. existing, operational Vestas V52 wind turbines, 8 no. turbines have a tip height of 91 m and a hub height of 65m, the remaining 3 no. turbines have a tip height of 76.1m and a hub height of 49m. All 11turbines have a rotor diameter of 52m. 1 no. existing operational onsite substation compound, the compound comprises: 38kV electrical substation, a control building, associated electrical plant and equipment, security fencing, associated underground cabling, existing site access tracks and 11 no. turbine hardstandings, existing operational site drainage infrastructure and associated works, including maintenance and improvement works. A Natura Impact Statement (NIS) and Environmental Impact Assessment Report (EIAR) have been prepared in relation to the project and accompany this planning application.
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "52-turbine wind farm with 91m turbines proposed at Gneeves Millstreet Co.Cork, Co. Cork", 26 November 2024. https://www.permission.ie/news/cork-county-council/24%2F6238
<p>Source: <a href="https://www.permission.ie/news/cork-county-council/24%2F6238">52-turbine wind farm with 91m turbines proposed at Gneeves Millstreet Co.Cork, Co. Cork</a>, Permission.ie analysis of the national planning register, 26 November 2024.</p>
Map, site boundary, timeline and nearby applications for 24/6238.
All wind energy applicationsThe full register view, with a map and decision statistics.
Get stories like this the day they are lodged
A county watch emails you every new application in Cork the week it appears.
Set up alerts