← Planning Wire

Wind energyDecisionCork

Cork County Council refuses permission for wind farm grid connection works at tSeithe Bheag (Shehy Beg), Co. Cork

14 May 2025 · Permission.ie Planning Wire · from the Cork County Council planning register · published 31 August 2026

Cork County Council refused permission on 14 May 2025 for a wind farm grid connection works at tSeithe Bheag (Shehy Beg), an application first lodged on 21 March 2025.

Key facts

Reference
25/142
Planning authority
Cork County Council
Location
tSeithe Bheag (Shehy Beg) Gortloughra Cloghboola & Inchinroe Co. Cork
Received
21 March 2025
Application type
Permission
Turbine height
175 m
Status
Appeal lodged
Decision
Refused
Decision date
14 May 2025

In context

It is one of 8 wind energy applications Cork County Council has received in the past twelve months, against 61 nationally. Of the 85 such applications decided by councils in the past three years, 74% were granted.

What happens next

The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 14 May 2025. If no appeal is lodged, the council’s decision stands and a final grant issues.

The development description, as lodged

Verbatim from the Cork County Council register. This is the source for every figure in the story above.

Erection of eight wind turbines with an overall ground to blade tip height of 175m consisting of a rotor diameter of 150m; and a hub height of 100m, Construction of permanent Turbine hardstands and Turbine Foundations, Construction of one temporary Construction Compound with associated temporary site offices parking areas and security fencing, Installation of meteorological mast with a height of 100m, Development of one on-site Borrow pit, Construction of new permanent internal site access roads and upgrade of existing internal site access roads to include passing bays and all associated drainage infrastructure, Development of a permanent internal site drainage network and sediment control systems, All associated underground electrical power and communications cabling connecting the wind turbines to the on-site substation, Biodiversity enhancement measures. Recreational community improvements including the erection of 4 no. permanent information boards relating to cultural heritage and upgrades to amenity tracks across the site, all associated site development works

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "Cork County Council refuses permission for wind farm grid connection works at tSeithe Bheag (Shehy Beg), Co. Cork", 14 May 2025. https://www.permission.ie/news/cork-county-council/25%2F142

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/cork-county-council/25%2F142">Cork County Council refuses permission for wind farm grid connection works at tSeithe Bheag (Shehy Beg), Co. Cork</a>, Permission.ie analysis of the national planning register, 14 May 2025.</p>
Full application record

Map, site boundary, timeline and nearby applications for 25/142.

All wind energy applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Cork the week it appears.

Set up alerts