Wind energyDecisionDonegal

Donegal County Council grants permission for 14-turbine wind farm with 100.5m turbines at AUGHT, TURE, Co. Donegal

30 November 2023 · Permission.ie Planning Wire · from the Donegal County Council planning register · published 15 September 2026

Donegal County Council granted permission on 30 November 2023 for a 14-turbine wind farm with 100.5m turbines at AUGHT, TURE, an application first lodged on 11 October 2023.

Key facts

Reference
2351543
Planning authority
Donegal County Council
Location
AUGHT, TURE, QUIGLEYS POINT
Received
11 October 2023
Application type
EXTENSION OF DURATION
Turbines
14
Turbine height
100.5 m
Permission sought
10 years
Status
APPLICATION FINALISED
Decision
UNCONDITIONAL
Decision date
30 November 2023

In context

It is one of 10 wind energy applications Donegal County Council has received in the past twelve months, against 60 nationally. Of the 84 such applications decided by councils in the past three years, 74% were granted.

What happens next

The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 30 November 2023. If no appeal is lodged, the council’s decision stands and a final grant issues. The applicant sought a 10-year permission, which sets how long they have to start the development.

The development description, as lodged

Verbatim from the Donegal County Council register. This is the source for every figure in the story above.

GRANT OF A 10 YEAR PLANNING PERMISSION FOR DEVELOPMENT OF A 14 TURBINE WIND FARM ON A SITE IN THE TOWNLAND OF AUGHT, APPROXIMATELY 5KM WEST OF QUIGLEY'S POINT. THE DEVELOPMENT WILL COMPRISE OF 14 NO ELECTRICITY GENERATING WIND TURBINES WITH A HUB HEIGHT OF 65 METRES AND A ROTOR DIAMETER OF 71 METRES GIVING AN OVERALL HEIGHT OF UP TO 100.5 METRES, HARDSTANDING, AN ELECTRICAL COMPOUND AND SUBSTATION BUILDING, ASSOCIATED SITE ROADS AND SITE WORKS. IT IS PROPOSED TO SOURCE ALL STONE FROM AN ON SITE BORROW PIT.

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "Donegal County Council grants permission for 14-turbine wind farm with 100.5m turbines at AUGHT, TURE, Co. Donegal", 30 November 2023. https://www.permission.ie/news/donegal-county-council/2351543

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/donegal-county-council/2351543">Donegal County Council grants permission for 14-turbine wind farm with 100.5m turbines at AUGHT, TURE, Co. Donegal</a>, Permission.ie analysis of the national planning register, 30 November 2023.</p>
Full application record

Map, site boundary, timeline and nearby applications for 2351543.

All wind energy applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Donegal the week it appears.

Set up alerts