Fingal County Council grants permission for 3.6-hectare solar farm at Cherryhound-Tyrrelstown M2/M3 link road, Co. Dublin
15 October 2026 · Permission.ie Planning Wire · from the Fingal County Council planning register · published 23 November 2026
Fingal County Council granted permission on 15 October 2026 for a 3.6-hectare solar farm at Cherryhound-Tyrrelstown M2/M3 link road, an application first lodged on 21 August 2026.
Key facts
- Reference
- FW26A/0329E
- Planning authority
- Fingal County Council
- Location
- Cherryhound-Tyrrelstown M2/M3 link road and west of the N2 interchange
- Received
- 21 August 2026
- Application type
- Permission
- Site area
- 3.6 hectares
- Status
- Decision Issued
- Decision
- GRANT PERMISSION
- Decision date
- 15 October 2026
In context
It is one of 16 solar farm applications Fingal County Council has received in the past twelve months, against 352 nationally. Of the 593 such applications decided by councils in the past three years, 92% were granted.
What happens next
The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 15 October 2026. If no appeal is lodged, the council’s decision stands and a final grant issues.
The development description, as lodged
Verbatim from the Fingal County Council register. This is the source for every figure in the story above.
The development will consist of revisions to the previously permitted Unit 3, which includes a main logistics/warehouse hall and ancillary office building (combined area of approximately 13,472 sqm) under Fingal County Council Reg. Ref. FW22A/0167. These revisions involve interior and exterior modifications to Unit 3 and associated external areas, resulting in a total net increase of c.197.50 sqm, gross floor area, on a site area of c.3.58Ha, including: I. Modification of the height (from 8.3 to 8 m) and footprint of the permitted ancillary office building, comprising retracting the eastern elevation and extending the building footprint towards the northern elevation, with infill of office entrance recesses to the south and reduction of recess to the north. II. Internal layout revisions and reconfiguration of spaces within Unit 3's main logistics/warehouse hall and ancillary office building, including increasing existing mezzanine space for mechanical plant. III. Changes to elevations and facades, including adjustments to fenestration, minor design feature modifications, and updates to materials; IV. Roof level revisions, including increased automatic ventilation openings, reduced permitted photovoltaic panels, 2 no. new roof access points, and relocation of an existing roof access; V. Relocation of the permitted ESB substation and associated switch room from within Unit 3 to an external area as a standalone structure (c. 43.5 sqm); VI. Revisions to the layout of permitted car, bicycle, and heavy goods vehicles (HGV) parking areas, resulting in a net reduction of 6 no. HGV parking spaces; VII. Minor revisions to exterior spaces, including omitting the permitted gatehouse, chemical storage and a section of footpath to south of the site, relocating the permitted refuse area and plant compound, and providing 1 no. pedestrian crossings along with 2 no. access gates and localised fencing (c. 2.4 m) for the permitted fire tender access route; and, VIII. All
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "Fingal County Council grants permission for 3.6-hectare solar farm at Cherryhound-Tyrrelstown M2/M3 link road, Co. Dublin", 15 October 2026. https://www.permission.ie/news/fingal-county-council/FW26A%2F0329E
<p>Source: <a href="https://www.permission.ie/news/fingal-county-council/FW26A%2F0329E">Fingal County Council grants permission for 3.6-hectare solar farm at Cherryhound-Tyrrelstown M2/M3 link road, Co. Dublin</a>, Permission.ie analysis of the national planning register, 15 October 2026.</p>
Map, site boundary, timeline and nearby applications for FW26A/0329E.
All solar farms applicationsThe full register view, with a map and decision statistics.
Get stories like this the day they are lodged
A county watch emails you every new application in Dublin the week it appears.
Set up alerts