Galway County Council grants permission for 11-turbine wind farm with 150m turbines at Knockranny Ardderroo Letter, Moycullen, Co. Galway

22 November 2023 · Permission.ie Planning Wire · from the Galway County Council planning register · published 1 September 2026

Galway County Council granted permission on 22 November 2023 for an 11-turbine wind farm with 150m turbines at Knockranny Ardderroo Letter, Moycullen, an application first lodged on 1 June 2023.

Key facts

Reference
23225
Planning authority
Galway County Council
Location
Knockranny Ardderroo Letter, Moycullen, Co. Galway
Received
1 June 2023
Application type
PERMISSION
Site area
77.8 hectares
Turbines
11
Turbine height
150 m
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision date
22 November 2023
Appeal
ABP-318723-23 · CONDITIONAL

In context

It is one of 3 wind energy applications Galway County Council has received in the past twelve months, against 60 nationally. Of the 84 such applications decided by councils in the past three years, 74% were granted.

What happens next

The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 22 November 2023. If no appeal is lodged, the council’s decision stands and a final grant issues.

The development description, as lodged

Verbatim from the Galway County Council register. This is the source for every figure in the story above.

for the following: (1) alterations to the Cnoc Raithní (Knockranny) Wind Farm (Galway County Council pl. ref. no. 13/829 & ABP ref: 07.243094 comprising 11no. wind turbines with an overall ground to blade tip height of 150m (an increase of 19.5m & 9.5m from 130.5m & 140.5m, as previously permitted), a rotor blade length of 68m or 69m & a hub height of 81m or 82m; associated increase in turbine foundations; & omission of permitted on-site 110kV substation & underground cabling; (2) provision of underground electrical (33kV) & communications cabling connecting the 11no. wind turbines to the Ardderroo wind farm substation for the purposes of connection to the national grid, including a new cable service track (with watercourse/culvert crossings) & widening of an existing access road; extension of the Ardderroo substation within the existing substation compound, including control building extension, new 110kV transformer & electrical plant & apparatus; (3) all associated site development & ancillary works above & below ground in support of the above, including site drainage & tree felling; (4) an operational period & planning permission duration to align with the existing permission (ABP ref: 07.243094). An Environmental Impact Assessment Report (EIAR) & Natura Impact Statement (NIS) have been prepared & will be submitted to the Planning Authority with the application

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "Galway County Council grants permission for 11-turbine wind farm with 150m turbines at Knockranny Ardderroo Letter, Moycullen, Co. Galway", 22 November 2023. https://www.permission.ie/news/galway-county-council/23225

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/galway-county-council/23225">Galway County Council grants permission for 11-turbine wind farm with 150m turbines at Knockranny Ardderroo Letter, Moycullen, Co. Galway</a>, Permission.ie analysis of the national planning register, 22 November 2023.</p>
Full application record

Map, site boundary, timeline and nearby applications for 23225.

All wind energy applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Galway the week it appears.

Set up alerts