Wind energyLodgedGalway
11-turbine wind farm with 150m turbines proposed at Moycullen, Co. Galway
21 July 2025 · Permission.ie Planning Wire · from the Galway County Council planning register · published 1 September 2026
An applicant lodged plans with Galway County Council on 21 July 2025 for an 11-turbine wind farm with 150m turbines at Moycullen. A decision is due by 14 September 2025.
Key facts
- Reference
- 25186
- Planning authority
- Galway County Council
- Location
- Cnoc Raithní Na hArd-Doiriú & Leitir, Moycullen, Co. Galway
- Received
- 21 July 2025
- Application type
- EXTENSION OF DURATION
- Site area
- 77.8 hectares
- Turbines
- 11
- Turbine height
- 150 m
- Status
- WITHDRAWN
- Decision due
- 14 September 2025
- Submissions until
- 24 August 2025 (closed)
In context
It is one of 3 wind energy applications Galway County Council has received in the past twelve months, against 61 nationally. Of the 85 such applications decided by councils in the past three years, 74% were granted.
What happens next
The five-week window for public submissions has closed. The council is due to decide by 14 September 2025, unless it requests further information, which stops the clock.
The development description, as lodged
Verbatim from the Galway County Council register. This is the source for every figure in the story above.
of pl. ref: 23/225 for the following: (1) alterations to the Cnoc Raithní (Knockranny) Wind Farm (Galway County Council pl. ref. no. 13/829 & ABP ref: 07.243094 comprising 11no. wind turbines with an overall ground to blade tip height of 150m (an increase of 19.5m & 9.5m from 130.5m & 140.5m, as previously permitted), a rotor blade length of 68m or 69m & a hub height of 81m or 82m; associated increase in turbine foundations; & omission of permitted on-site 110kV substation & underground cabling; (2) provision of underground electrical (33kV) & communications cabling connecting the 11no. wind turbines to the Ardderroo wind farm substation for the purposes of connection to the national grid, including a new cable service track (with watercourse/culvert crossings) & widening of an existing access road; extension of the Ardderroo substation within the existing substation compound, including control building extension, new 110kV transformer & electrical plant & apparatus; (3) all associated site development & ancillary works above & below ground in support of the above, including site drainage & tree felling; (4) an operational period & planning permission duration to align with the existing permission (ABP ref: 07.243094). An Environmental Impact Assessment Report (EIAR) & Natura Impact Statement (NIS) have been prepared & will be submitted to the Planning Authority with the application
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "11-turbine wind farm with 150m turbines proposed at Moycullen, Co. Galway", 21 July 2025. https://www.permission.ie/news/galway-county-council/25186
<p>Source: <a href="https://www.permission.ie/news/galway-county-council/25186">11-turbine wind farm with 150m turbines proposed at Moycullen, Co. Galway</a>, Permission.ie analysis of the national planning register, 21 July 2025.</p>
Map, site boundary, timeline and nearby applications for 25186.
All wind energy applicationsThe full register view, with a map and decision statistics.
Get stories like this the day they are lodged
A county watch emails you every new application in Galway the week it appears.
Set up alerts