An applicant lodged plans with Galway County Council on 18 September 2026 for a wind farm grid connection works at Leitir, Moycullen. Submissions from the public can be made until 22 October 2026, and a decision is due by 12 November 2026.
Key facts
- Reference
- 2661584
- Planning authority
- Galway County Council
- Location
- Leitir, Moycullen, Co. Galway
- Received
- 18 September 2026
- Application type
- PERMISSION
- Site area
- 10.3 hectares
- Status
- NEW APPLICATION
- Decision due
- 12 November 2026
- Submissions until
- 22 October 2026
In context
It is one of 3 wind energy applications Galway County Council has received in the past twelve months, against 60 nationally. Of the 82 such applications decided by councils in the past three years, 74% were granted.
What happens next
Anyone can make a submission or observation to Galway County Council until 22 October 2026, for a fee of €20. Only those who make a submission can later appeal the decision. The council is due to decide by 12 November 2026, unless it requests further information, which stops the clock.
The development description, as lodged
Verbatim from the Galway County Council register. This is the source for every figure in the story above.
for; (1) Amendments to the permitted Ardderroo Synchronous Condenser (Galway County Council Reference No. 23/60641, 24/61485, 25/60575 and 25/61825) comprising repositioning of cooling equipment and provision of 1 no. container within the synchronous condenser compound, a revised footprint of the 110kV electrical compound, revision of the 110kV underground cabling route to Knockranny substation and provision of a new access road and widening of the existing road to accommodate the revised underground electrical cabling. (2) Amendment to the Knockranny Wind Farm grid connection (permitted under An Coimisiún Pleanála Reference No. PL07.318723), comprising revised underground electrical (33kV) and communications cabling route to connect to the 110kV electrical compound. A Natura Impact Statement (NIS) has been prepared in respect of the proposed development. Beidh an fhorbairt bheartaithe comhdhéanta de: (1) Leasuithe ar an gComhdhlúthadóir Sioncronach Ardderroo ceadaithe (Uimhreacha Tagartha Chomhairle Chontae na Gaillimhe 23/60641, 24/61485, 25/60575 agus 25/61825) lena n-áirítear athshuíomh trealaimh fhuaraithe agus soláthar de 1 uimh. coimeádáin laistigh de chomhdhúil an chomhdhlúthadóra shioncronach, lorg athbhreithnithe do chomhdhúil leictreach 110kV, athbhreithniú ar an mbealach cáblaithe 110kV faoi thalamh go dtí fostáisiún Knockranny agus soláthar bóthair rochtana nua agus leathnú an bhóthair reatha chun freastal ar an gcábla leictreach faoi thalamh athbhreithnithe. (2) Leasú ar nasc eangach Feirm Gaoithe Knockranny (ceadaithe faoi Uimhir Thagartha An Coimisiún Pleanála PL07.318723), lena n-áirítear bealach athbhreithnithe do chábla leictreach (33kV) agus cumarsáide faoi thalamh chun nascadh leis an gcomhdhúil leictreach 110kV. Ullmhaíodh Ráiteas Tionchair Natura (NIS) i ndáil leis an bhforbairt bheartaithe
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "Changes sought to permitted wind farm grid connection works at Leitir, Moycullen, Co. Galway", 18 September 2026. https://www.permission.ie/news/galway-county-council/2661584
<p>Source: <a href="https://www.permission.ie/news/galway-county-council/2661584">Changes sought to permitted wind farm grid connection works at Leitir, Moycullen, Co. Galway</a>, Permission.ie analysis of the national planning register, 18 September 2026.</p>
Map, site boundary, timeline and nearby applications for 2661584.
All wind energy applicationsThe full register view, with a map and decision statistics.
Get stories like this the day they are lodged
A county watch emails you every new application in Galway the week it appears.
Set up alerts