← Planning Wire

Solar farmsDecisionKildare

Kildare County Council refuses permission for 105 MW solar farm at Naas, Co. Kildare

6 February 2025 · Permission.ie Planning Wire · from the Kildare County Council planning register · published 1 September 2026

Kildare County Council refused permission on 6 February 2025 for a 105 MW solar farm at Naas, an application first lodged on 2 February 2024.

Key facts

Reference
2460079
Planning authority
Kildare County Council
Location
Townlands of Flemingtown South (otherwith known as Tonaphuca) Donode Big Sillagh and Swordlestown South, Naas, Co. Kildare
Received
2 February 2024
Application type
PERMISSION
Site area
128.6 hectares
Stated capacity
105 MW
Operational life
10 years
Status
APPEALED
Decision
REFUSED
Decision date
6 February 2025
Appeal
ABP-322016-25

In context

It is one of 12 solar farm applications Kildare County Council has received in the past twelve months, against 333 nationally. Of the 572 such applications decided by councils in the past three years, 92% were granted.

What happens next

The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 6 February 2025. If no appeal is lodged, the council’s decision stands and a final grant issues.

The development description, as lodged

Verbatim from the Kildare County Council register. This is the source for every figure in the story above.

for a period of 10 years to construct and complete a solar PV Energy Development with a total site area of 128.66 hectares comprising of electrical and inverter substations, modules, solar PV ground mounted on support structures, temporary construction compounds, internal access tracks, security fencing, electrical cabling and ducting, CCTV and other ancillary infrastructure. The solar farm would be operational for 40 years. A Natura Impact Statement (NIS) will be submitted with the application. The export capacity to the grid is estimated be c. 105MW MEC. Revised by Significant Further Information which consists of the addition of a temporary construction access which has been included within the red and blue line boundaries

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "Kildare County Council refuses permission for 105 MW solar farm at Naas, Co. Kildare", 6 February 2025. https://www.permission.ie/news/kildare-county-council/2460079

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/kildare-county-council/2460079">Kildare County Council refuses permission for 105 MW solar farm at Naas, Co. Kildare</a>, Permission.ie analysis of the national planning register, 6 February 2025.</p>
Full application record

Map, site boundary, timeline and nearby applications for 2460079.

All solar farms applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Kildare the week it appears.

Set up alerts
Kildare County Council refuses permission for 105 MW solar farm at Naas, Co. Kildare | Permission.ie