Kildare County Council refuses permission for 56 MW solar farm at Mulgeeth and Mucklon, Co. Kildare
4 February 2025 · Permission.ie Planning Wire · from the Kildare County Council planning register · published 1 September 2026
Kildare County Council refused permission on 4 February 2025 for a 56 MW solar farm at Mulgeeth and Mucklon, an application first lodged on 24 June 2024.
Key facts
- Reference
- 2460568
- Planning authority
- Kildare County Council
- Location
- Townlands of, Mulgeeth and Mucklon, Co. Kildare
- Received
- 24 June 2024
- Application type
- PERMISSION
- Site area
- 80.9 hectares
- Stated capacity
- 56 MW
- Operational life
- 10 years
- Status
- APPLICATION FINALISED
- Decision
- REFUSED
- Decision date
- 4 February 2025
- Appeal
- ABP-321991-25 · CONDITIONAL
In context
It is one of 12 solar farm applications Kildare County Council has received in the past twelve months, against 333 nationally. Of the 572 such applications decided by councils in the past three years, 92% were granted.
What happens next
The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 4 February 2025. If no appeal is lodged, the council’s decision stands and a final grant issues.
The development description, as lodged
Verbatim from the Kildare County Council register. This is the source for every figure in the story above.
for a period of 10 years to construct and complete a solar PV energy development with a total site area of 80.9 hectares, comprising of the construction of PV panels mounted on metal frames, transformer stations, GRP units, internal access tracks, perimeter fencing with CCTV cameras and access gates, electrical cabling and ducting, temporary construction compounds, widening of an existing entrance, landscaping and all ancillary infrastructure and associated works. The solar farm would be operational for 35 years. The export capacity to grid is estimated to be c. 56MW MEC. A Natura Impact Statement (NIS) has been prepared in respect of this application. Revised by Significant Further Information which consists of additional passing bays have been included in the Construction Traffic Management Plan
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "Kildare County Council refuses permission for 56 MW solar farm at Mulgeeth and Mucklon, Co. Kildare", 4 February 2025. https://www.permission.ie/news/kildare-county-council/2460568
<p>Source: <a href="https://www.permission.ie/news/kildare-county-council/2460568">Kildare County Council refuses permission for 56 MW solar farm at Mulgeeth and Mucklon, Co. Kildare</a>, Permission.ie analysis of the national planning register, 4 February 2025.</p>
Map, site boundary, timeline and nearby applications for 2460568.
All solar farms applicationsThe full register view, with a map and decision statistics.
Get stories like this the day they are lodged
A county watch emails you every new application in Kildare the week it appears.
Set up alerts