Kildare County Council refuses permission for 56 MW solar farm at Mulgeeth and Mucklon, Co. Kildare

4 February 2025 · Permission.ie Planning Wire · from the Kildare County Council planning register · published 1 September 2026

Kildare County Council refused permission on 4 February 2025 for a 56 MW solar farm at Mulgeeth and Mucklon, an application first lodged on 24 June 2024.

Key facts

Reference
2460568
Planning authority
Kildare County Council
Location
Townlands of, Mulgeeth and Mucklon, Co. Kildare
Received
24 June 2024
Application type
PERMISSION
Site area
80.9 hectares
Stated capacity
56 MW
Operational life
10 years
Status
APPLICATION FINALISED
Decision
REFUSED
Decision date
4 February 2025
Appeal
ABP-321991-25 · CONDITIONAL

In context

It is one of 12 solar farm applications Kildare County Council has received in the past twelve months, against 333 nationally. Of the 572 such applications decided by councils in the past three years, 92% were granted.

What happens next

The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 4 February 2025. If no appeal is lodged, the council’s decision stands and a final grant issues.

The development description, as lodged

Verbatim from the Kildare County Council register. This is the source for every figure in the story above.

for a period of 10 years to construct and complete a solar PV energy development with a total site area of 80.9 hectares, comprising of the construction of PV panels mounted on metal frames, transformer stations, GRP units, internal access tracks, perimeter fencing with CCTV cameras and access gates, electrical cabling and ducting, temporary construction compounds, widening of an existing entrance, landscaping and all ancillary infrastructure and associated works. The solar farm would be operational for 35 years. The export capacity to grid is estimated to be c. 56MW MEC. A Natura Impact Statement (NIS) has been prepared in respect of this application. Revised by Significant Further Information which consists of additional passing bays have been included in the Construction Traffic Management Plan

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "Kildare County Council refuses permission for 56 MW solar farm at Mulgeeth and Mucklon, Co. Kildare", 4 February 2025. https://www.permission.ie/news/kildare-county-council/2460568

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/kildare-county-council/2460568">Kildare County Council refuses permission for 56 MW solar farm at Mulgeeth and Mucklon, Co. Kildare</a>, Permission.ie analysis of the national planning register, 4 February 2025.</p>
Full application record

Map, site boundary, timeline and nearby applications for 2460568.

All solar farms applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Kildare the week it appears.

Set up alerts
Kildare County Council refuses permission for 56 MW solar farm at Mulgeeth and Mucklon, Co. Kildare | Permission.ie