Kildare County Council refuses permission for 35 MW solar farm at Kilglass, Co. Kildare

16 January 2026 · Permission.ie Planning Wire · from the Kildare County Council planning register · published 1 September 2026

Kildare County Council refused permission on 16 January 2026 for a 35 MW solar farm at Kilglass, an application first lodged on 20 March 2025.

Key facts

Reference
2560291
Planning authority
Kildare County Council
Location
Townland of, Kilglass, Co. Kildare
Received
20 March 2025
Application type
PERMISSION
Site area
45.9 hectares
Stated capacity
35 MW
Operational life
10 years
Status
APPEALED
Decision
REFUSED
Decision date
16 January 2026
Appeal
PL-500767-KE-26

In context

It is one of 12 solar farm applications Kildare County Council has received in the past twelve months, against 337 nationally. Of the 573 such applications decided by councils in the past three years, 92% were granted.

What happens next

The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 16 January 2026. If no appeal is lodged, the council’s decision stands and a final grant issues.

The development description, as lodged

Verbatim from the Kildare County Council register. This is the source for every figure in the story above.

for a period of 10 years to construct and complete a solar PV energy development with a total site area of 45.9 hectares, comprising of the construction of PV panels mounted on metal frames, transformer stations, GRP unit, internal access tracks, perimeter fencing with CCTV cameras and access gates, electrical cabling and ducting, temporary construction compound, landscaping and all ancillary infrastructure and associated works. The solar farm would be operational for 35 years. The export capacity to grid is estimated to be c. 35MW MEC. A Natura Impact Statement (NIS) has been prepared in respect of this application

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "Kildare County Council refuses permission for 35 MW solar farm at Kilglass, Co. Kildare", 16 January 2026. https://www.permission.ie/news/kildare-county-council/2560291

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/kildare-county-council/2560291">Kildare County Council refuses permission for 35 MW solar farm at Kilglass, Co. Kildare</a>, Permission.ie analysis of the national planning register, 16 January 2026.</p>
Full application record

Map, site boundary, timeline and nearby applications for 2560291.

All solar farms applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Kildare the week it appears.

Set up alerts