Solar farmsLodgedKildare

32 MW solar farm proposed at Coolnafearagh, Monasterevin, Co. Kildare

12 September 2025 · Permission.ie Planning Wire · from the Kildare County Council planning register · published 1 September 2026

An applicant lodged plans with Kildare County Council on 12 September 2025 for a 32 MW solar farm at Coolnafearagh, Monasterevin. The application seeks an operational life of 40 years.

Key facts

Reference
2561050
Planning authority
Kildare County Council
Location
Townland of Coolnafearagh, Monasterevin, Co. Kildare
Received
12 September 2025
Application type
PERMISSION
Site area
37.7 hectares
Stated capacity
32 MW
Operational life
40 years
Status
INCOMPLETED APPLICATION
Submissions until
16 October 2025 (closed)

In context

It is one of 12 solar farm applications Kildare County Council has received in the past twelve months, against 335 nationally. Of the 573 such applications decided by councils in the past three years, 92% were granted.

What happens next

The five-week window for public submissions has closed. The council normally decides within eight weeks of the application being lodged, unless it requests further information, which stops the clock.

The development description, as lodged

Verbatim from the Kildare County Council register. This is the source for every figure in the story above.

for • Linear arrays of solar PV panels on ground mounted steel supported structures with associated cabling and ducting; • 4 no. proposed single storey inverter stations; • All associated underground cabling (within and between land parcels), including onsite control and switch gear room; • Site Perimeter fencing; • 2 no. new site entrances with palisade double security gates; • 2 no. temporary construction compound/carpark/material storage areas with associated temporary site offices, parking areas and security fencing; • 3 no. temporary and 1 no. permanent steel storage containers; • Site access tracks including passing and turning bays; • On-site pole mounted CCTV cameras; • 2 no. bottomless culverts; • 2 no. temporary construction stage Moby Dick type wheel wash systems; • 1 no. Concrete wash out location (within the westernmost temporary construction compound); and • All associated and ancillary works. The proposed solar farm development spans a total site area measuring 60.36 ha, of which 37.66 ha is located in Co. Kildare and 22.7 ha is located in Co. Laois. Permission is sought for a period of 10 years with an operational period of 40 years. The total capacity of Solar PV on the site is estimated to be 32 MW

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "32 MW solar farm proposed at Coolnafearagh, Monasterevin, Co. Kildare", 12 September 2025. https://www.permission.ie/news/kildare-county-council/2561050

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/kildare-county-council/2561050">32 MW solar farm proposed at Coolnafearagh, Monasterevin, Co. Kildare</a>, Permission.ie analysis of the national planning register, 12 September 2025.</p>
Full application record

Map, site boundary, timeline and nearby applications for 2561050.

All solar farms applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Kildare the week it appears.

Set up alerts