← Planning Wire

Wind energyDecisionLaois

Laois County Council refuses permission for wind turbine delivery route at Tinwear Archerstown and Durrow, Co. Laois

2 September 2025 · Permission.ie Planning Wire · from the Laois County Council planning register · published 1 September 2026

Laois County Council refused permission on 2 September 2025 for a wind turbine delivery route at Tinwear Archerstown and Durrow, an application first lodged on 9 July 2025.

Key facts

Reference
2560414
Planning authority
Laois County Council
Location
Tinwear Archerstown and Durrow, Co. Laois
Received
9 July 2025
Application type
PERMISSION
Site area
14.9 hectares
Turbines
2
Turbine height
175 m
Permission sought
10 years
Operational life
35 years
Status
APPEALED
Decision
REFUSED
Decision date
2 September 2025
Appeal
ACP-323775-25

In context

There were 61 nationally in the past twelve months. Of the 85 such applications decided by councils in the past three years, 74% were granted.

What happens next

The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 2 September 2025. If no appeal is lodged, the council’s decision stands and a final grant issues. The applicant sought a 10-year permission, which sets how long they have to start the development.

The development description, as lodged

Verbatim from the Laois County Council register. This is the source for every figure in the story above.

i. construct 2 no. wind turbines with an overall turbine tip height of 175 metres; a rotor blade diameter of 150 metres; and hub height of 100 metres, and associated foundations and hard standing areas; ii. Upgrade of existing tracks and roads and the provision of new site access roads; iii. Underground electrical and communications cabling connecting the wind turbines to a proposed 38kV on-site substation located in the townland of Ballynaslee Co. Kilkenny; iv. Accommodation works along the N77 National secondary road in the townland of Durrow Townparks, Co. Laois to facilitate the delivery of turbine components and other abnormal sized loads; v. Hedgerow Removal; vi. Biodiversity Management and Enhancement Plan measures (including establishment of new hedgerow, translocation of existing hedgerow and enhancement of existing hedgerow); vii. Spoil Management; viii. Site Drainage; ix. Operational stage site signage; and, x. All associated site development works, ancillary works and apparatus. A 10-year planning permission and 35-year operational life from the date of commissioning of the entire wind farm is being sought. An Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) accompany this planning application

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "Laois County Council refuses permission for wind turbine delivery route at Tinwear Archerstown and Durrow, Co. Laois", 2 September 2025. https://www.permission.ie/news/laois-county-council/2560414

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/laois-county-council/2560414">Laois County Council refuses permission for wind turbine delivery route at Tinwear Archerstown and  Durrow, Co. Laois</a>, Permission.ie analysis of the national planning register, 2 September 2025.</p>
Full application record

Map, site boundary, timeline and nearby applications for 2560414.

All wind energy applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Laois the week it appears.

Set up alerts
Laois County Council refuses permission for wind turbine delivery route at Tinwear Archerstown and Durrow, Co. Laois | Permission.ie