Leitrim County Council refuses permission for 4-turbine wind farm with 50m turbines at Drumkeeran, Co. Leitrim

13 March 2024 · Permission.ie Planning Wire · from the Leitrim County Council planning register · published 15 September 2026

Leitrim County Council refused permission on 13 March 2024 for a 4-turbine wind farm with 50m turbines at Drumkeeran, an application first lodged on 19 January 2024.

Key facts

Reference
2460008
Planning authority
Leitrim County Council
Location
Letter Boleybaun Stangaun Greaghnadarragh Corralustia Turpaun Gortnasillagh West Lugmeeltan Leckaun Lisgavneen Treannadullagh Drumcashlagh and Corderry, Drumkeeran, County Leitrim
Received
19 January 2024
Application type
PERMISSION
Site area
45 hectares
Turbines
4
Turbine height
50 m
Operational life
40 years
Status
APPLICATION FINALISED
Decision
REFUSED
Decision date
13 March 2024
Appeal
ABP-319480-24 · REFUSED

In context

It is the only wind energy application Leitrim County Council has received in the past twelve months, against 63 nationally. Of the 84 such applications decided by councils in the past three years, 74% were granted.

What happens next

The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 13 March 2024. If no appeal is lodged, the council’s decision stands and a final grant issues.

The development description, as lodged

Verbatim from the Leitrim County Council register. This is the source for every figure in the story above.

ten year planning permission with a 40-year operational life (from the date of commissioning of the development). (ii) Construction of 4 No. wind turbines with an overall ground to blade tip height ranging from 149.85m to 150m inclusive. The wind turbines will have a rotor diameter ranging from 115.7m to 117m inclusive and a hub height ranging from 91.5m to 92m inclusive. (iii) Construction of permanent turbine hardstands and turbine foundations. (iv) Construction of a bottomless bridge culvert across a minor stream on site (EPA River Segment Code: 26_4053). (v) Construction of one temporary construction compound with associated temporary site offices, parking areas and security fencing. (vi) Installation of one (40-year life cycle) meteorological mast with a height of 50m and a 4m lightning pole on top. (vii) Construction of new internal site access tracks and upgrade of a section of existing internal Site track, to include all associated drainage. (viii) Improvement of existing site entrance with access via the L4282. (ix) Development of an internal site drainage network and sediment control systems. (x) Construction of 1 no. permanent 20kV electrical substation. (xi) All associated underground electrical and communications cabling connecting the wind turbines to the wind farm substation. (xii) All works associated with the connection of the wind farm to the national electricity grid, which will be via 20kV underground and partially overhead cable connection approximately 6.4km in length to the existing ESB Corderry 110kV Substation in the townlands of Letter, Greaghnadarragh, Stangaun, Corralustia, Turpaun, Gortnasillagh West, Lugmeeltan, Leckaun, Lisgavneen, Treannadullagh, Drumcashlagh and Corderry. (xiii) Ancillary forestry felling to facilitate construction of the development. (xiv) All associated site development works including berms, landscaping, and soil excavation. (xv) Installation of battery arrays located within container units (2 no. units) and associated electrical plant for grid stabilisation adjacent to the substation building. (xvi) Development of one on-site borrow pit.

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "Leitrim County Council refuses permission for 4-turbine wind farm with 50m turbines at Drumkeeran, Co. Leitrim", 13 March 2024. https://www.permission.ie/news/leitrim-county-council/2460008

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/leitrim-county-council/2460008">Leitrim County Council refuses permission for 4-turbine wind farm with 50m turbines at Drumkeeran, Co. Leitrim</a>, Permission.ie analysis of the national planning register, 13 March 2024.</p>
Full application record

Map, site boundary, timeline and nearby applications for 2460008.

All wind energy applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Leitrim the week it appears.

Set up alerts
Leitrim County Council refuses permission for 4-turbine wind farm with 50m turbines at Drumkeeran, Co. Leitrim | Permission.ie