← Planning Wire · Limerick County Council news

Solar farmsLodgedLimerick

19.6-hectare solar farm proposed at Lisnagry, Co. Limerick

29 September 2026 · Permission.ie Planning Wire · from the Limerick County Council planning register · published 17 November 2026

An applicant lodged plans with Limerick County Council on 29 September 2026 for a 19.6-hectare solar farm at Lisnagry. The application seeks an operational life of 40 years. A decision is due by 13 November 2026.

Key facts

Reference
2661142
Planning authority
Limerick County Council
Location
Grange Upper & Grange Lower, Lisnagry, Co. Limerick
Received
29 September 2026
Application type
PERMISSION
Site area
19.6 hectares
Operational life
40 years
Status
NEW APPLICATION
Decision due
13 November 2026
Submissions until
2 November 2026 (closed)

In context

It is one of 23 solar farm applications Limerick County Council has received in the past twelve months, against 343 nationally. Of the 561 such applications decided by councils in the past three years, 92% were granted.

What happens next

The five-week window for public submissions has closed. The council is due to decide by 13 November 2026, unless it requests further information, which stops the clock.

The development description, as lodged

Verbatim from the Limerick County Council register. This is the source for every figure in the story above.

a solar photovoltaic farm and co-located Battery Energy Storage System within an application area of approximately 19.57 hectares, comprising ground-mounted solar panels; 34 no. inverter units; 2 no. containerised LV/MV transformer stations; 4 no. battery enclosures; 2 no. Power Conversion System units; a substation building and an underground 10.5 kV grid connection to Ahane 110 kV substation, including an HDD crossing beneath the railway. The development will also include underground cabling; fencing; a gated entrance from the R506; access tracks; CCTV cameras; a temporary construction compound; a public water-main connection; a sealed underground foul-water tank with no public-sewer connection; drainage; landscaping, biodiversity measures and associated works. Construction and operational access will be from the new R506 entrance. Permission is sought for 10 years, with an operational period of 40 years. A Natura impact Statement has been prepared and will be submitted with the application. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "19.6-hectare solar farm proposed at Lisnagry, Co. Limerick", 29 September 2026. https://www.permission.ie/news/limerick-city-and-county-council/2661142

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/limerick-city-and-county-council/2661142">19.6-hectare solar farm proposed at Lisnagry, Co. Limerick</a>, Permission.ie analysis of the national planning register, 29 September 2026.</p>
Full application record

Map, site boundary, timeline and nearby applications for 2661142.

All solar farms applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Limerick the week it appears.

Set up alerts