11.2-hectare solar farm proposed at Shanmullagh, Ballinamuck, Co. Longford

6 February 2026 · Permission.ie Planning Wire · from the Longford County Council planning register · published 1 September 2026

An applicant lodged plans with Longford County Council on 6 February 2026 for an 11.2-hectare solar farm at Shanmullagh, Ballinamuck. The application seeks a 10-year permission.

Key facts

Reference
2660037
Planning authority
Longford County Council
Location
in the townland of Shanmullagh, Ballinamuck, County Longford
Received
6 February 2026
Application type
PERMISSION
Site area
11.2 hectares
Permission sought
10 years
Status
INCOMPLETED APPLICATION
Submissions until
12 March 2026 (closed)

In context

It is one of 4 solar farm applications Longford County Council has received in the past twelve months, against 337 nationally. Of the 573 such applications decided by councils in the past three years, 92% were granted.

What happens next

The five-week window for public submissions has closed. The council normally decides within eight weeks of the application being lodged, unless it requests further information, which stops the clock.

The development description, as lodged

Verbatim from the Longford County Council register. This is the source for every figure in the story above.

a 10 Year Planning Permission for a solar farm with a total area of circa 11 hectares. The solar farm will consist of solar panels on ground mounted frames, 14 no. single storey electrical inverter stations and 1 no. single storey electrical LV/MV transformer station, 2 no. single storey spare parts containers, 1 no. Ring Main Units, 1 no. MV substation, underground electrical ducting and cabling within the development site, security fencing, CCTV, access tracks, temporary construction compounds, landscaping and all associated ancillary development and drainage works. The proposed development will connect into the existing 20kV overhead electricity line that crosses the site. Construction and operational vehicle access will be via 1 no. new entrance from the L-10193 public road. The operational lifespan of the solar farm will be 40 years and planning permission is requested for this duration. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413)

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "11.2-hectare solar farm proposed at Shanmullagh, Ballinamuck, Co. Longford", 6 February 2026. https://www.permission.ie/news/longford-county-council/2660037

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/longford-county-council/2660037">11.2-hectare solar farm proposed at Shanmullagh, Ballinamuck, Co. Longford</a>, Permission.ie analysis of the national planning register, 6 February 2026.</p>
Full application record

Map, site boundary, timeline and nearby applications for 2660037.

All solar farms applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Longford the week it appears.

Set up alerts