← Planning Wire

Wind energyDecisionLouth

Louth County Council grants permission for 5-turbine wind farm at C, Co. Louth

10 December 2025 · Permission.ie Planning Wire · from the Louth County Council planning register · published 1 September 2026

Louth County Council granted permission on 10 December 2025 for a 5-turbine wind farm at C, an application first lodged on 4 December 2024.

Key facts

Reference
2460766
Planning authority
Louth County Council
Location
Kellystown Wind Farm Ballymakenny Brownstown Carntown Carstown Cartanstown Castletown Drumshallon Gallstown Groom Kearneystown Keeverstown Killineer Mell Newtown Monasterboice Piperstown Stonehouse Swinestown Tullyallen Tullyard, and Tullyeskar, C
Received
4 December 2024
Application type
PERMISSION
Site area
83.3 hectares
Turbines
5
Status
APPEALED
Decision
CONDITIONAL
Decision date
10 December 2025
Appeal
PL-500624-LH-26

In context

There were 61 nationally in the past twelve months. Of the 85 such applications decided by councils in the past three years, 74% were granted.

What happens next

The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 10 December 2025. If no appeal is lodged, the council’s decision stands and a final grant issues.

The development description, as lodged

Verbatim from the Louth County Council register. This is the source for every figure in the story above.

Permission for proposed development to consist of: (i) The construction of 5 no. wind turbines with the following parameters: a) Total tip height range of 179.5m – 180m, b) Rotor diameter range of 149m – 163m, c) Hub height range of 98m to 105m, (ii) Construction of turbine foundations, crane hardstand areas and assembly areas; (iii) All associated wind farm underground electrical and communications cabling connecting the turbines and meteorological mast to the proposed onsite electrical substation including cabling. in the public road corridor in the townlands of Gallstown and Kearneystown; (iv) Construction of 1 no. permanent 38kV electrical substation compound including a single-storey control building with welfare facilities, all associated electrical plant and equipment, security fencing, gates, all associated underground cabling, wastewater holding tank, and all ancillary structures and works in the townland of Piperstown. (v) A Battery Energy Storage System within the 38kV electrical substation compound; (vi) All works associated with the connection of the proposed wind farm to the national electricity grid which includes 5 no. of water crossings (3 no. bridges and 2 no. culverts). The provision of joint bays and associated communication chambers along the underground electrical cabling route via underground 38kV electrical cabling predominantly within the public road corridor, from the onsite substation in the townland of Piperstown to the existing Drybridge 110 kV Substation located in the townland of Tullyallen; (vii) Reinstatement of all road and track surfaces above cabling trench along existing roads and tracks in public lands; (viii) Provision of new site access tracks and upgrade of existing site tracks/roads to facilitate access to all onsite infrastructure this includes 3 no. water crossings, passing bays and all associated drainage; (ix) The provision of 2 no. new permanent site entrances for construction and operational access from the local road L6274 in the townlands of Kearneystown and Gallstown; (x) The permanent realignment of 1 no. existing entrance for construction and operational access to the 38kV electrical substation compound from the local road L2275 in the townland of Piperstown; (xi) Use of 1 no. existing site entrance for construction, operational access to the permanent met mast on a private road off local road L2275 in the townland of Drumshallon. (xii) The construction of 1 no. new temporary track in the townland o

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "Louth County Council grants permission for 5-turbine wind farm at C, Co. Louth", 10 December 2025. https://www.permission.ie/news/louth-county-council/2460766

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/louth-county-council/2460766">Louth County Council grants permission for 5-turbine wind farm at C, Co. Louth</a>, Permission.ie analysis of the national planning register, 10 December 2025.</p>
Full application record

Map, site boundary, timeline and nearby applications for 2460766.

All wind energy applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Louth the week it appears.

Set up alerts
Louth County Council grants permission for 5-turbine wind farm at C, Co. Louth | Permission.ie