← Planning Wire · Mayo County Council news

Wind energyLodgedMayo

Wind turbine delivery route proposed at Ballynacloy Aghamore Ballyhaunis, Co. Mayo

30 October 2026 · Permission.ie Planning Wire · from the Mayo County Council planning register · published 17 November 2026

HARRINGTON CONCRETE AND QUARRIES ULC lodged plans with Mayo County Council on 30 October 2026 for a wind turbine delivery route at Ballynacloy Aghamore Ballyhaunis. The application seeks an operational life of 35 years. Submissions from the public can be made until 3 December 2026, and a decision is due by 2 January 2027.

Key facts

Reference
2660867
Planning authority
Mayo County Council
Location
Liscosker Rath Ballyhine Carrowscoltia Scardaun and, Ballynacloy Aghamore Ballyhaunis, Co Mayo.
Applicant
HARRINGTON CONCRETE AND QUARRIES ULC
Received
30 October 2026
Application type
PERMISSION
Site area
28.1 hectares
Stated capacity
2 MW
Turbines
1
Operational life
35 years
Status
NEW APPLICATION
Decision due
2 January 2027
Submissions until
3 December 2026

In context

It is one of 7 wind energy applications Mayo County Council has received in the past twelve months, against 62 nationally. Of the 78 such applications decided by councils in the past three years, 74% were granted.

What happens next

Anyone can make a submission or observation to Mayo County Council until 3 December 2026, for a fee of €20. Only those who make a submission can later appeal the decision. The council is due to decide by 2 January 2027, unless it requests further information, which stops the clock.

How to make a submission

The development description, as lodged

Verbatim from the Mayo County Council register. This is the source for every figure in the story above.

We, HARRINGTON CONCRETE AND QUARRIES ULC, intend to apply to Mayo County Council for planning permission for a single wind turbine. The proposed development will be located in the townlands of Liscosker, Rath, Carrowscoltia, Scardaun, Ballynacloy and Ballyhine, Aghamore, Ballyhaunis, Co. Mayo. The development will consist of: • Erection of a turbine with dimensions of 150m tip height. • Construction of a crane hardstand of c. 1,075m2 to allow erection of the turbine. • The upgrade of c. 1,640m in length of existing internal quarry roads. • The construction of new access track of c. 200m in length and 4.5m in width minimum from the existing quarry road to the proposed turbine location. • A cable duct of c.1,606m from the proposed turbine to the existing on-site substation (located approx. 570m northwest of the proposed turbine location). • A Battery Energy Storage System (BESS) facility compound with a capacity to store approximately 2MW of energy from the turbine. • Widening works at 2 no. locations on the haul route to facilitate delivery of turbine components. This application is seeking a ten-year permission and a 35 year operational period from the date of overall commissioning of the entire wind farm. The planning application is accompanied by an Appropriate Assessment Screening. The Application may be inspected, or purchased at a fee not exceeding the reasonable cost of making a copy, at the office of the Planning Section, Mayo County Council, Áras an Contae, The Mall, Castlebar, County Mayo, during its public opening hours. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application is subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply. A submission or observation in relation to the application may be made in writing to the planning authority on payment of the prescribed fee (€20) within the period of 5 weeks beginning on the date of receipt by the Authority of the application and such submissions or observations will be considered by the planning authority in making a decision on the application. The planning authority may grant permission subject to or without conditions, or may refuse to grant permission.

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "Wind turbine delivery route proposed at Ballynacloy Aghamore Ballyhaunis, Co. Mayo", 30 October 2026. https://www.permission.ie/news/mayo-county-council/2660867

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/mayo-county-council/2660867">Wind turbine delivery route proposed at Ballynacloy Aghamore Ballyhaunis, Co. Mayo</a>, Permission.ie analysis of the national planning register, 30 October 2026.</p>
Full application record

Map, site boundary, timeline and nearby applications for 2660867.

All wind energy applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Mayo the week it appears.

Set up alerts