Meath County Council grants permission for 6.8-hectare solar farm at Peterstown, Trim, Co. Meath

7 August 2025 · Permission.ie Planning Wire · from the Meath County Council planning register · published 1 September 2026

Meath County Council granted permission on 7 August 2025 for a 6.8-hectare solar farm at Peterstown, Trim, an application first lodged on 25 September 2024.

Key facts

Reference
24383
Planning authority
Meath County Council
Location
Peterstown, Trim, Co. Meath
Received
25 September 2024
Application type
PERMISSION
Site area
6.8 hectares
Permission sought
10 years
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision date
7 August 2025

In context

It is one of 17 solar farm applications Meath County Council has received in the past twelve months, against 335 nationally. Of the 573 such applications decided by councils in the past three years, 92% were granted.

What happens next

The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 7 August 2025. If no appeal is lodged, the council’s decision stands and a final grant issues. The applicant sought a 10-year permission, which sets how long they have to start the development.

The development description, as lodged

Verbatim from the Meath County Council register. This is the source for every figure in the story above.

a 10 year planning permission for development of a Solar PV Panel Array consisting of up to 10,000 no. Solar PV Panels (c.27,010m2) on ground mounted steel frames on a c. 6.76 hectare site, ESB Substation, Power Inverter Units, Underground Cable Ducts, Perimeter Security Fence, CCTV Masts, Solar Lighting and all associated works. Significant further information/revised Plans submitted on this application

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "Meath County Council grants permission for 6.8-hectare solar farm at Peterstown, Trim, Co. Meath", 7 August 2025. https://www.permission.ie/news/meath-county-council/24383

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/meath-county-council/24383">Meath County Council grants permission for 6.8-hectare solar farm at Peterstown, Trim, Co. Meath</a>, Permission.ie analysis of the national planning register, 7 August 2025.</p>
Full application record

Map, site boundary, timeline and nearby applications for 24383.

All solar farms applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Meath the week it appears.

Set up alerts