Meath County Council grants permission for 19.48 MW solar farm at Commons Carranstown and Platin, Co. Meath
1 May 2026 · Permission.ie Planning Wire · from the Meath County Council planning register · published 1 September 2026
Meath County Council granted permission on 1 May 2026 for a 19.48 MW solar farm at Commons Carranstown and Platin, an application first lodged on 12 December 2025.
Key facts
- Reference
- 2561187
- Planning authority
- Meath County Council
- Location
- Townlands of Commons Carranstown and Platin, accessed off the L1609 Station Road Duleek, County Meath
- Received
- 12 December 2025
- Application type
- PERMISSION
- Site area
- 22.4 hectares
- Stated capacity
- 19.48 MW
- Status
- APPEALED
- Decision
- CONDITIONAL
- Decision date
- 1 May 2026
- Appeal
- PL-501323-MH-26
- Council file
- View on the Meath County Council planning portal
In context
It is one of 17 solar farm applications Meath County Council has received in the past twelve months, against 337 nationally. Of the 573 such applications decided by councils in the past three years, 92% were granted.
What happens next
The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 1 May 2026. If no appeal is lodged, the council’s decision stands and a final grant issues.
The development description, as lodged
Verbatim from the Meath County Council register. This is the source for every figure in the story above.
RED III - Erection of a 19.48 MWp ground-mounted Solar Photovoltaic (PV) farm on lands off Station Road located to the west of Platin Cement Works and associated quarry north of Duleek, Co. Meath. The project will occupy approximately 22.35 hectares of agricultural fields adjacent to the existing cement facility and is designed to directly supply renewable electricity to the plant, thereby improving its energy efficiency and sustainability profile. The development will consist of photovoltaic panels mounted on fixed-tilt frames oriented to the south, with associated underground cabling and electrical infrastructure, including three transformer cabins and inverters. It will also include internal access tracks, a temporary construction compound and set-down area, perimeter security fencing, and CCTV where required. The grid connection will be made via the existing on-site substation at the Irish Cement Plant, enabling the generated power to be consumed on-site. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provision of article 26A of the Planning & Development Regulations 2001 to 2025 shall apply.
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "Meath County Council grants permission for 19.48 MW solar farm at Commons Carranstown and Platin, Co. Meath", 1 May 2026. https://www.permission.ie/news/meath-county-council/2561187
<p>Source: <a href="https://www.permission.ie/news/meath-county-council/2561187">Meath County Council grants permission for 19.48 MW solar farm at Commons Carranstown and Platin, Co. Meath</a>, Permission.ie analysis of the national planning register, 1 May 2026.</p>
Map, site boundary, timeline and nearby applications for 2561187.
All solar farms applicationsThe full register view, with a map and decision statistics.