Solar farmsLodgedOffaly

145 MW solar farm proposed at STONESTOWN, KILCAMIN CRANCREAGH, Co. Offaly

12 December 2025 · Permission.ie Planning Wire · from the Offaly County Council planning register · published 1 September 2026

An applicant lodged plans with Offaly County Council on 12 December 2025 for a 145 MW solar farm at STONESTOWN, KILCAMIN CRANCREAGH. The application seeks an operational life of 40 years.

Key facts

Reference
25130
Planning authority
Offaly County Council
Location
STONESTOWN, KILCAMIN CRANCREAGH, DERRINLOUGH CO.OFFALY
Received
12 December 2025
Application type
PERMISSION
Site area
148 hectares
Stated capacity
145 MW
Operational life
40 years
Status
INCOMPLETED APPLICATION
Submissions until
24 January 2026 (closed)

In context

It is one of 28 solar farm applications Offaly County Council has received in the past twelve months, against 337 nationally. Of the 573 such applications decided by councils in the past three years, 92% were granted.

What happens next

The five-week window for public submissions has closed. The council normally decides within eight weeks of the application being lodged, unless it requests further information, which stops the clock.

The development description, as lodged

Verbatim from the Offaly County Council register. This is the source for every figure in the story above.

A PERIOD OF 10 YEARS, WITH AN OPERATIONAL LIFE OF 40 YEARS FROM THE DATE OF COMMISSIONING. THE PROPOSED DEVELOPMENT COMPRISES OF A SOLAR PHOTOVOLTAIC (PV) FARM AND ALL ASSOCIATED WORKS. THIS APPLICATION INVOLVES THE INSTALLATION OF 145MW OF SOLAR PV OVER AN APPROXIMATE AREA OF 148 HECTARES, INCLUDING 41 NO. TRANSFORMERS AND 1 NO. RMU. THE PROPOSED DEVELOPMENT WILL UTILISE 1 NO. EXISTING CONSTRUCTION ENTRANCE, AND 2 NO. EXISTING OPERATIONAL ENTRANCES. THE PROPOSED DEVELOPMENT WILL UTILISE EXISTING INTERNAL ACCESS TRACKS AND WILL INVOLVE THE CONSTRUCTION OF APPROXIMATELY 7KM OF NEW INTERNAL ACCESS TRACKS. THE SITE IS CENTRED AT X (ITM) 608494.8003 AND Y (ITM) 716388.2449. A NATURA IMPACT STATEMENT WILL ALSO BE SUBMITTED TO THE THE PLANNING AUTHORITY WITH THIS APPLICATION. THE DEVELOPMENT IS COVERED BY THE PROVISIONS OF THE RENEWABLE ENERGY DIRECTIVE III (DIRECTIVE 2023/2413).

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "145 MW solar farm proposed at STONESTOWN, KILCAMIN CRANCREAGH, Co. Offaly", 12 December 2025. https://www.permission.ie/news/offaly-county-council/25130

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/offaly-county-council/25130">145 MW solar farm proposed at STONESTOWN, KILCAMIN CRANCREAGH, Co. Offaly</a>, Permission.ie analysis of the national planning register, 12 December 2025.</p>
Full application record

Map, site boundary, timeline and nearby applications for 25130.

All solar farms applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Offaly the week it appears.

Set up alerts