Offaly County Council granted permission on 11 June 2025 for a 1.5-hectare solar farm at Portarlington, an application first lodged on 23 January 2025.
Key facts
- Reference
- 2560018
- Planning authority
- Offaly County Council
- Location
- Kilmalogue Park and Kilmalogue and Shanderry, Portarlington, County Offaly
- Received
- 23 January 2025
- Application type
- PERMISSION
- Site area
- 1.5 hectares
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision date
- 11 June 2025
In context
It is one of 28 solar farm applications Offaly County Council has received in the past twelve months, against 335 nationally. Of the 573 such applications decided by councils in the past three years, 92% were granted.
What happens next
The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 11 June 2025. If no appeal is lodged, the council’s decision stands and a final grant issues.
The development description, as lodged
Verbatim from the Offaly County Council register. This is the source for every figure in the story above.
The development will consist of the creation and use of a temporary vehicular access onto the public carriageway at Kilmalogue Park for use for the construction of a permitted 10KV single storey substation and its associated operational access track both previously permitted under Planning Ref. No. 17/275 as revised by Planning Ref. 23/196 as part of a solar farm development. The proposed development will comprise the temporary removal of a section of an existing boundary wall (c. 5.4m) at Kilmalogue Park, the provision of a temporary construction track, ancillary development works, full reinstatement of the wall upon completion of the construction of the permitted substation and an increase in the area of permanent gravel track around the substation. The development will be used for the construction of the permitted substation in lieu of a previously permitted construction access track permitted under Planning Ref. No. 17/275 for the construction of the substation.
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "Offaly County Council grants permission for 1.5-hectare solar farm at Portarlington, Co. Offaly", 11 June 2025. https://www.permission.ie/news/offaly-county-council/2560018
<p>Source: <a href="https://www.permission.ie/news/offaly-county-council/2560018">Offaly County Council grants permission for 1.5-hectare solar farm at Portarlington, Co. Offaly</a>, Permission.ie analysis of the national planning register, 11 June 2025.</p>
Map, site boundary, timeline and nearby applications for 2560018.
All solar farms applicationsThe full register view, with a map and decision statistics.
Get stories like this the day they are lodged
A county watch emails you every new application in Offaly the week it appears.
Set up alerts