Offaly County Council grants permission for 137-hectare solar farm at Srah Wood and Greenhills, Rhode, Co. Offaly

6 October 2025 · Permission.ie Planning Wire · from the Offaly County Council planning register · published 1 September 2026

Offaly County Council granted permission on 6 October 2025 for a 137-hectare solar farm at Srah Wood and Greenhills, Rhode, an application first lodged on 20 March 2025.

Key facts

Reference
2560082
Planning authority
Offaly County Council
Location
Srah Wood and Greenhills, Rhode, County Offaly
Received
20 March 2025
Application type
PERMISSION
Site area
137 hectares
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision date
6 October 2025

In context

It is one of 28 solar farm applications Offaly County Council has received in the past twelve months, against 335 nationally. Of the 573 such applications decided by councils in the past three years, 92% were granted.

What happens next

The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 6 October 2025. If no appeal is lodged, the council’s decision stands and a final grant issues.

The development description, as lodged

Verbatim from the Offaly County Council register. This is the source for every figure in the story above.

Amendments to the development permitted under Offaly County Council Planning Register Reference 20/494 to: (i) revise the layout of the permitted development including solar array and inverter/transformer units; (ii) increase the height of the permitted solar array from 2.914 metres to up to 3.3 metres; (iii) provide for variable spacings between the solar array rows; (iv) provide for varying solar array tilt-angles; (v) alter the design of the electrical inverter/transformer units and reduce the number of electrical inverter/transformer units from 27 no. to 14 no.; (vi) revise the alignment of approximately 250 metres of existing on-site access tracks and construct approximately 7,500 metres of access track; (vii) relocate and redesign the permitted battery energy storage system compound including an increase in the compound footprint from approximately 3,850 square metres to approximately 10,100 square metres; (viii) alter the design of the battery energy storage system and increase the number of battery energy storage system and ancillary containers from 38 no. to 83 no.; (ix) alter Condition No. 6(b) to provide for the planting of screening vegetation at the end of the construction phase; (x) alter Condition No. 5(a) to provide for the decommissioning of the development no later than 40-years from the date of commissioning; and, (xi) all associated site development, drainage, access and reinstatement works. This planning application is accompanied by a Natura Impact Statement (NIS)

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "Offaly County Council grants permission for 137-hectare solar farm at Srah Wood and Greenhills, Rhode, Co. Offaly", 6 October 2025. https://www.permission.ie/news/offaly-county-council/2560082

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/offaly-county-council/2560082">Offaly County Council grants permission for 137-hectare solar farm at Srah Wood and Greenhills, Rhode, Co. Offaly</a>, Permission.ie analysis of the national planning register, 6 October 2025.</p>
Full application record

Map, site boundary, timeline and nearby applications for 2560082.

All solar farms applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Offaly the week it appears.

Set up alerts