← Planning Wire

Solar farmsLodgedRoscommon

10 MW solar farm proposed at Ardagawna, Drum, Co. Roscommon

19 August 2026 · Permission.ie Planning Wire · from the Roscommon County Council planning register · published 1 September 2026

Eirgen Power Limited lodged plans with Roscommon County Council on 19 August 2026 for a 10 MW solar farm at Ardagawna, Drum. The application seeks an operational life of 40 years. Submissions from the public can be made until 22 September 2026.

Key facts

Reference
2660426
Planning authority
Roscommon County Council
Location
Ardagawna, Drum, Athlone
Applicant
Eirgen Power Limited
Received
19 August 2026
Application type
PERMISSION
Site area
16.3 hectares
Stated capacity
10 MW
Operational life
40 years
Status
PRE_VALIDATION
Submissions until
22 September 2026

In context

It is one of 9 solar farm applications Roscommon County Council has received in the past twelve months, against 339 nationally. Of the 573 such applications decided by councils in the past three years, 92% were granted.

What happens next

Anyone can make a submission or observation to Roscommon County Council until 22 September 2026, for a fee of €20. Only those who make a submission can later appeal the decision. The council normally decides within eight weeks of the application being lodged, unless it requests further information, which stops the clock.

How to make a submission

The development description, as lodged

Verbatim from the Roscommon County Council register. This is the source for every figure in the story above.

We, Eirgen Power Limited, intend to apply for permission for development at this site at Ardagawna, Drum, Athlone, Co. Roscommon. The development will consist of a relevant solar farm development comprising: i. Installation of PV panels on ground mounted frames in rows with a max height of 3.2m. ii. An ESB electricity substation compound including single storey substation building and electrical infrastructure. iii. Up to 6 no. single inverter stations (or an alternative string inverter provision). iv. Internal underground electrical and communications cabling and ducting. v. Use of already approved farm access tracks (PD/26/60040) and provision of additional new internal access tracks vi. All ancillary site development works and landscaping, including temporary construction compound, deer-type fencing, security fencing, security gates and CCTV cameras. vii. Widening of existing west site-entrance and relocation of existing east site-entrance. viii. Construction access via L75814, post-construction ESB maintenance access via L20271. ix. The decommissioning and reinstatement of the solar farm at the end of its operational life. x. On a site area of approximately 16.3 hectares. xi. A Natura Impact Statement accompanies this submission. The solar farm will have an operational lifespan of 40 years and an estimated export capacity of approx. 10MW of electricity. Planning permission is sought for a period of 10 years for construction, with an operational life of 40 years from the date of commissioning, including the decommissioning and reinstatement of the solar farm at the end of its operational life. In accordance with Article 239 of the Planning and Development Regulations 2001 (as amended), notice is hereby given: a) that a Natura Impact Statement will be submitted to the planning authority with the application, and b) that the Natura Impact Statement will be available for inspection or purchase at a fee not exceeding the reasonable cost of making a copy during office hours at the office of the planning authority. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply. The planning

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "10 MW solar farm proposed at Ardagawna, Drum, Co. Roscommon", 19 August 2026. https://www.permission.ie/news/roscommon-county-council/2660426

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/roscommon-county-council/2660426">10 MW solar farm proposed at Ardagawna, Drum, Co. Roscommon</a>, Permission.ie analysis of the national planning register, 19 August 2026.</p>
Full application record

Map, site boundary, timeline and nearby applications for 2660426.

All solar farms applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Roscommon the week it appears.

Set up alerts