Wind energyDecisionSligo
Sligo County Council grants permission for wind farm grid connection works at Riverstown, Gorteen, Co. Sligo
4 July 2024 · Permission.ie Planning Wire · from the Sligo County Council planning register · published 1 September 2026
Sligo County Council granted permission on 4 July 2024 for a wind farm grid connection works at Riverstown, Gorteen, an application first lodged on 24 October 2023.
Key facts
- Reference
- 2360288
- Planning authority
- Sligo County Council
- Location
- Riverstown, Gorteen, Co. Sligo
- Received
- 24 October 2023
- Application type
- PERMISSION
- Site area
- 4.2 hectares
- Stated capacity
- 3.5 MW
- Turbine height
- 180 m
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision date
- 4 July 2024
- Appeal
- ABP-320302-24 · CONDITIONAL
- Council file
- View on the Sligo County Council planning portal
In context
It is the only wind energy application Sligo County Council has received in the past twelve months, against 61 nationally. Of the 84 such applications decided by councils in the past three years, 74% were granted.
What happens next
The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 4 July 2024. If no appeal is lodged, the council’s decision stands and a final grant issues.
The development description, as lodged
Verbatim from the Sligo County Council register. This is the source for every figure in the story above.
Planning permission for a renewable wind energy development of a one (1) turbine wind farm. The proposed development will be located in the townland of Riverstown, approximately 2.2km north of Gorteen, Co. Sligo. The development will comprise of one (1) electricity generating wind turbine, which will have an overall maximum tip height of 180 meters, comprising a tower of nominally 112 meters high, and rotor diameter of up to 136 meters. The development will consist of permanent access tracks, hardstandings, an electrical substation building, an underground cable trench and ancillary site works. The maximum output capacity of the wind farm will be c.3.5mw.
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "Sligo County Council grants permission for wind farm grid connection works at Riverstown, Gorteen, Co. Sligo", 4 July 2024. https://www.permission.ie/news/sligo-county-council/2360288
<p>Source: <a href="https://www.permission.ie/news/sligo-county-council/2360288">Sligo County Council grants permission for wind farm grid connection works at Riverstown, Gorteen, Co. Sligo</a>, Permission.ie analysis of the national planning register, 4 July 2024.</p>
Map, site boundary, timeline and nearby applications for 2360288.
All wind energy applicationsThe full register view, with a map and decision statistics.
Get stories like this the day they are lodged
A county watch emails you every new application in Sligo the week it appears.
Set up alerts