Solar farmsLodgedTipperary
88.5-hectare solar farm proposed at Kerane Fawnlough and Ballynaclough, Nenagh, Co. Tipperary
26 January 2024 · Permission.ie Planning Wire · from the Tipperary County Council planning register · published 15 September 2026
An applicant lodged plans with Tipperary County Council on 26 January 2024 for an 88.5-hectare solar farm at Kerane Fawnlough and Ballynaclough, Nenagh. The application seeks a 10-year permission.
Key facts
- Reference
- 2460051
- Planning authority
- Tipperary County Council
- Location
- Townlands of Kerane Fawnlough and Ballynaclough, Nenagh, County Tipperary
- Received
- 26 January 2024
- Application type
- PERMISSION
- Site area
- 88.5 hectares
- Permission sought
- 10 years
- Status
- INCOMPLETED APPLICATION
- Submissions until
- 29 February 2024 (closed)
In context
It is one of 20 solar farm applications Tipperary County Council has received in the past twelve months, against 351 nationally. Of the 572 such applications decided by councils in the past three years, 92% were granted.
What happens next
The five-week window for public submissions has closed. The council normally decides within eight weeks of the application being lodged, unless it requests further information, which stops the clock.
The development description, as lodged
Verbatim from the Tipperary County Council register. This is the source for every figure in the story above.
permission for development at this site within the townlands of Kerane, Fawnlough and Ballynaclough, Nenagh, Co. Tipperary. The development will consist of a 10-year planning permission to construct and complete a solar PV Energy Development with a total site area of c. 88.5 hectares comprising of inverter substations, modules, solar PV ground mounted on support structures, temporary construction compounds, internal access tracks, security fencing, electrical cabling and ducting, CCTV and other ancillary infrastructure. The solar farm would be operational for 40 years. A Natura Impact Statement (NIS) will be submitted with the application.
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "88.5-hectare solar farm proposed at Kerane Fawnlough and Ballynaclough, Nenagh, Co. Tipperary", 26 January 2024. https://www.permission.ie/news/tipperary-county-council/2460051
<p>Source: <a href="https://www.permission.ie/news/tipperary-county-council/2460051">88.5-hectare solar farm proposed at Kerane Fawnlough and Ballynaclough, Nenagh, Co. Tipperary</a>, Permission.ie analysis of the national planning register, 26 January 2024.</p>
Map, site boundary, timeline and nearby applications for 2460051.
All solar farms applicationsThe full register view, with a map and decision statistics.