Wicklow County Council granted permission on 28 November 2024 for a 1 MW solar farm at Goldenfort, Baltinglass, an application first lodged on 11 October 2024.

Key facts

Reference
2460627
Planning authority
Wicklow County Council
Location
Goldenfort, Baltinglass, County Wicklow
Received
11 October 2024
Application type
PERMISSION
Site area
1.7 hectares
Stated capacity
1 MW
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision date
28 November 2024

In context

It is one of 10 solar farm applications Wicklow County Council has received in the past twelve months, against 333 nationally. Of the 572 such applications decided by councils in the past three years, 92% were granted.

What happens next

The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 28 November 2024. If no appeal is lodged, the council’s decision stands and a final grant issues.

The development description, as lodged

Verbatim from the Wicklow County Council register. This is the source for every figure in the story above.

the erection and operation of a c. 1MW photovoltaic energy development on c. 1.65ha, which includes fixed panels on ground mounted frames, customer/ESB substation unit which will be connected to the national grid with overhead line, electrical transformers, inverters, switchgear, underground cabling and ducting, boundary fencing, security entrance gates, CCTV, internal access road and all associated ancillary activities. The operational lifespan will be 35 years. A five-year planning permission is being sought

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "Wicklow County Council grants permission for 1 MW solar farm at Goldenfort, Baltinglass, Co. Wicklow", 28 November 2024. https://www.permission.ie/news/wicklow-county-council/2460627

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/wicklow-county-council/2460627">Wicklow County Council grants permission for 1 MW solar farm at Goldenfort, Baltinglass, Co. Wicklow</a>, Permission.ie analysis of the national planning register, 28 November 2024.</p>
Full application record

Map, site boundary, timeline and nearby applications for 2460627.

All solar farms applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Wicklow the week it appears.

Set up alerts