65.4-hectare solar farm proposed at Mullycagh Upper, Co. Wicklow

28 March 2025 · Permission.ie Planning Wire · from the Wicklow County Council planning register · published 1 September 2026

An applicant lodged plans with Wicklow County Council on 28 March 2025 for a 65.4-hectare solar farm at Mullycagh Upper.

Key facts

Reference
2560226
Planning authority
Wicklow County Council
Location
Mullycagh Upper, Co. Wicklow
Received
28 March 2025
Application type
PERMISSION
Site area
65.4 hectares
Status
INCOMPLETED APPLICATION
Submissions until
1 May 2025 (closed)

In context

It is one of 10 solar farm applications Wicklow County Council has received in the past twelve months, against 335 nationally. Of the 573 such applications decided by councils in the past three years, 92% were granted.

What happens next

The five-week window for public submissions has closed. The council normally decides within eight weeks of the application being lodged, unless it requests further information, which stops the clock.

The development description, as lodged

Verbatim from the Wicklow County Council register. This is the source for every figure in the story above.

development which will consist of the construction of a Solar PV development, a Battery Energy Storage System facility (BESS) and all ancillary works on a ca. 65.4 ha site consisting of: (I) Solar PV panels laid out in arrays across the Site; (ii)A 38kV substation building ((13.8 (l) and 7.4 (w)) and associated compound area, (iii)a transformer unit (ca. 5.8m x ca. 8.45m) and associated bund; (iv)192 number Battery Energy Storage System units comprising 22 modules (ca. 3.1m x ca.3.1m); (iv)6 MV Skid/Power Hubs (ca. 9.45m x ca.2.1m), (v)24 number inverter units (ca. 3m x ca.2.6m); (vi)Upgrade of 1 No. existing Site entrance; (vii)1 No. temporary construction compound; (viii)Electrical and communications cabling; (ix)Pole-mounted security cameras; (x)Perimeter security fencing (2m high) and security gates; (xi)Internal access tracks; and, (xii)All associated ancillary development, landscaping and reinstatement works The operational lifetime of the proposed development will be 40-years. A Natura Impact Statement will accompany the planning application

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "65.4-hectare solar farm proposed at Mullycagh Upper, Co. Wicklow", 28 March 2025. https://www.permission.ie/news/wicklow-county-council/2560226

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/wicklow-county-council/2560226">65.4-hectare solar farm proposed at Mullycagh Upper, Co. Wicklow</a>, Permission.ie analysis of the national planning register, 28 March 2025.</p>
Full application record

Map, site boundary, timeline and nearby applications for 2560226.

All solar farms applications

The full register view, with a map and decision statistics.

Get stories like this the day they are lodged

A county watch emails you every new application in Wicklow the week it appears.

Set up alerts
65.4-hectare solar farm proposed at Mullycagh Upper, Co. Wicklow | Permission.ie