6.3-hectare solar farm proposed at Vartry Waterworks, Roundwood Oldtown, Co. Wicklow
17 September 2026 · Permission.ie Planning Wire · from the Wicklow County Council planning register · published 29 September 2026
An applicant lodged plans with Wicklow County Council on 17 September 2026 for a 6.3-hectare solar farm at Vartry Waterworks, Roundwood Oldtown. The application seeks a 10-year permission. Submissions from the public can be made until 21 October 2026, and a decision is due by 11 November 2026.
Key facts
- Reference
- 2660840
- Planning authority
- Wicklow County Council
- Location
- Vartry Waterworks, Roundwood Oldtown, Knockfadda Newastle Upper
- Received
- 17 September 2026
- Application type
- PERMISSION
- Site area
- 6.3 hectares
- Permission sought
- 10 years
- Status
- NEW APPLICATION
- Decision due
- 11 November 2026
- Submissions until
- 21 October 2026
In context
It is one of 11 solar farm applications Wicklow County Council has received in the past twelve months, against 346 nationally. Of the 562 such applications decided by councils in the past three years, 93% were granted.
What happens next
Anyone can make a submission or observation to Wicklow County Council until 21 October 2026, for a fee of €20. Only those who make a submission can later appeal the decision. The council is due to decide by 11 November 2026, unless it requests further information, which stops the clock.
The development description, as lodged
Verbatim from the Wicklow County Council register. This is the source for every figure in the story above.
10-year planning permission for the Vartry Security of supply project at the existing Vartry waterworks site south of the Vartry reservoir in the townlands of Roundwood in the electoral division of Oldtown, and Knockfadda in the electoral division of Newcastle Upper, County Wicklow, the proposed development consists of, i) 60 megalitres treated water storage in two new 30 megalitres capacity structures, ii) a new underground dichlorination chamber, iii) a permanent pre-cast concrete bridge over the Vartry River on existing bridge abutments, iv) solar photovoltaic panels installation on both reservoir roof areas, v) a temporary storage area for excavated material, vi) ancillary works including, a. water supply pipes, b. surface water drainage, c. temporary lighting during the construction stage only, d. temporary compound area for the construction period, e. hardstanding adjacent to the existing Callowhill Pumphouse, f. extension of internal access road to the inlet / outlet chamber of the reservoirs and, g. associated landscaping works
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "6.3-hectare solar farm proposed at Vartry Waterworks, Roundwood Oldtown, Co. Wicklow", 17 September 2026. https://www.permission.ie/news/wicklow-county-council/2660840
<p>Source: <a href="https://www.permission.ie/news/wicklow-county-council/2660840">6.3-hectare solar farm proposed at Vartry Waterworks, Roundwood Oldtown, Co. Wicklow</a>, Permission.ie analysis of the national planning register, 17 September 2026.</p>
Map, site boundary, timeline and nearby applications for 2660840.
All solar farms applicationsThe full register view, with a map and decision statistics.
Get stories like this the day they are lodged
A county watch emails you every new application in Wicklow the week it appears.
Set up alerts