DERRYVACORNEEN, DERRYVACORNEEN,

CONDITIONAL

Planning application 00/5815

Cork - Cork County Council

Application Timeline

  1. Application received

    26 Sept 2000

  2. Decision: CONDITIONAL

    5 Sept 2001

  3. Decision due

    27 Sept 2001

  4. Grant issued

    8 Oct 2001

Application Details

Location
DERRYVACORNEEN, DERRYVACORNEEN,
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
26 September 2000Other applications received that week
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
5 September 2001
Grant Date
8 October 2001

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

856m
05/9688REFUSED22 Dec 2005

8 no. wind turbines each turbine with an overall height of 107 m. , access roads , control building and substation compound and ancillary works

Derryvacorneen Carraggnamuck,Ballingeary

981m
01/2968CONDITIONAL25 May 2001

Erection of temporary 50m high monitoring mast with wind speed & direction sensors

DERRYVACORNEEN, DERRYVACORNEEN,

1.1km
09/401WITHDRAWN9 Apr 2009

Construction of eight wind turbines in the townlands of Dooneens, Inchi More, Tooreennanean, Tooreenduff and Derryvacorneen, Ballingeary, Co. Cork. Wind turbine base to tip heights are as follows: 2x119m, 5x126m and 1x139m. This renewable energy development will include a permission 80 meter meteorological mast, substation compound with control house, onsite tracks, 2 proposed borrow pits, underground cabling & associated works

Dooneens. Inchi More. Tooreennanean. Tooreenduff. Derryvacorneen. Ballyingeary, Co. Cork.

1.3km
09/256INCOMPLETED APPLICATION9 Mar 2009

Construction of eight wind turbines; Wind turbine base to tip heights are as follows: 2x119m, 5x126m and 1x139m. This renewable energy development will include a permanent 80 meter meteorological mast, substation compound with control base, onsite tracks, 2 proposed borrow pits, underground cabling and associated site works

Dooneens, Inchi More Tooreennanean Tooreenduff, Derryvacorneen Ballingeary

1.4km
18/29CONDITIONAL22 Jan 2018

The continuation of use for an 18.3 metre high tower with associated equipment attached and with equipment containers and cabinets at ground level all within a chain-link fence compound using existing access. This application is subsequent to a conditional decision to grant permission for the development by Cork County Council reference number 11/00011

Illauninagh West Td Ballingeary Co. Cork

1.4km
11/11CONDITIONAL12 Jan 2011

Retention of an 18.3 metre high tower with associated equipment attached and with equipment cabinets at ground level all within a chain-link fence compound using existing access

Illauninagh West Ballingeary Co. Cork

1.4km
99/7133CONDITIONAL22 Dec 1999

Retention of GSM Antennas on RTE mast

ILLAUNINAGH WEST, ILLAUNINAGH WEST,

1.4km
00/6095CONDITIONAL10 Oct 2000

Erection of telecommunications equipment comprising antennae onto existing RTE mast & equipment cabin in existing compound

RTE BALLINGEARY- RTE BALLINGEARY- SITE, ILLAUNINAGH WEST,

1.4km
02/2837CONDITIONAL2 Jul 2002

Retention of 18.3m high telecommunications tower, antennas & equipment cabin

ILLAUNINAGH WEST, ILLAUNINAGH WEST,

1.4km
12/673CONDITIONAL30 Oct 2012

Dwelling and proprietary treatment unit

Kealvaugh Beg Ballingeary Macroom Co. Cork

Planning a project of your own?