Application Timeline

  1. Application received

    2 Feb 2011

  2. Decision due

    29 Mar 2011

  3. Decision: CONDITIONAL

    29 Mar 2011

  4. Grant issued

    4 May 2011

Application Details

Location
Derryroe Macroom Co Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
2 February 2011
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
29 March 2011
Grant Date
4 May 2011

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

4m
09/7326CONDITIONAL14 Oct 2009

Extension to general purpose shed

Derryroe Macroom

4m
06/7878CONDITIONAL7 Jun 2006

Construct loose cattle and feed storage shed and retain general purpose house and extension to slatted house

Derryroe Macroom

5m
24/4338CONDITIONAL28 Feb 2024

1) Retention of cubicle house as constructed, 2) construction of cubicle house with underground slurry storage tanks and 3) construction of feed storage shed/machinery shed/cattle shed with under ground slurry storage tank and all associated site works.

Derryroe Macroom Co.Cork

8m
25/6104Grant with Conditions6 Oct 2025

Permission to install a milk silo tank and all associated site works

Derryroe, Macroom, Co. Cork

356m
26/1982Awaiting Recommendation24 Jul 2026

The development will consist of the following elements: i. A Battery Energy Storage System (BESS) facility with a storage capacity of 130-150 MW, consisting of battery containers with HVAC units, transformers, inverters, underground cabling, 2 No. associated control rooms, internal access routes, parking, lighting, CCTV, lightning masts, fencing. ii. A solar PV array with an export capacity of 3 MW, comprising of ground-mounted panels on metal frames, together with associated inverters, transformer station, lighting, CCTV, fencing and internal electrical and communications cabling. iii. Operations and Electrical Compound consisting of: a) Low voltage operations compound including three (3) operations containers (switchgear room, control & metering room and communications room), outdoor electrical plant, above ground and underground cabling, lighting, CCTV, diesel generator and diesel tank, welfare and office container, storage containers and waste storage areas, and adjoining; b) High voltage electrical compound (TSO and IPP compound) comprising outdoor electrical plant, transformers, cabling, lighting, CCTV, lightning masts, fencing. iv. Underground high voltage electrical cable to facilitate a connection to the existing 110/220kV Clashavoon substation. v. New entrances and access roads (1 No. main access and 1 No. emergency access) to the site from the L7473 local road including 1 no. stream crossing; and vi. all associated drainage and ancillary works necessary to facilitate the development A 10 year permission and a 40 year operational period is sought in respect of this planning application. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply.

In the townlands of Derryroe, Macroom and Kilberrihert, Coachford, Co. Cork

356m
26/0335Invalid - Case Closed13 Feb 2026

The development will consist of a Battery Energy Storage System (BESS) facility and Solar Farm comprising of the following elements: i. A Battery Energy Storage System (BESS) compound, consisting of battery containers with HVAC units, transformers, inverters, underground cabling, 2 No. associated control rooms, internal access routes, parking, lighting, CCTV, lightning masts, fencing. ii. A solar PV array comprising of ground-mounted panels on metal frames, together with associated inverters, transformer station, lighting, CCTV, fencing and internal electrical and communications cabling. iii. Operations and Electrical Compound consisting of: (a) Low voltage operations compound including three (3) operations containers (switchgear room, control & metering room and communications room), outdoor electrical plant, above ground and underground cabling, lighting, CCTV, diesel generator and diesel tank, welfare and office container, storage containers and waste storage areas, and adjoining; (b) High voltage electrical compound (TSO and IPP compound) comprising outdoor electrical plant, transformers, cabling, lighting, CCTV, lightning masts, fencing. iv. Underground high voltage electrical cable to facilitate a connection to the existing 110/220kV Clashavoon substation. v. New entrances and access roads (1 No. main access and 1 No. emergency access) to the site from the L-7473 local road including 1 no. stream crossing; and vi. all associated drainage and ancillary works necessary to facilitate the development A 10 year permission is sought in respect of the development. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply.

In the townlands of Derryroe and Kilberrihert, Co. Cork

386m
04/2138CONDITIONAL1 Apr 2004

Extension to dwellinghouse, construction of domestic garage and retention of extension to dwelling

Derryroe Macroom

432m
20/6866CONDITIONAL17 Dec 2020

a) Permission for retention of dwelling to include revised boundaries, entrance and site layout including septic tank, all as constructed, and b) Permission for decommissioning of existing septic tank and soakpit and construction of new septic tank and percolation area.

Derryroe Macroom Co. Cork

469m
26/1265Awaiting F.I. Response13 May 2026

Permission to construct extension to western side of existing dwelling. Permission to remove roof of existing dwelling and to construct a new raised roof including repositioning of front and Gable windows and Permission to install a domestic wastewater treatment system and all associated site works.

Derryroe, Macroom, Co. Cork.

528m
06/5382CONDITIONAL9 Mar 2006

Slatted unit and asociated slurry tanks, feeding passage, handling area and silage slab

Derryroe Macroom

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?