← Back to search

Depuy (Ireland) Loughbeg Ringaskiddy

INCOMPLETED APPLICATION

Planning application 11/5954

Cork - Cork County Council

Proposed Development

  1. (a)
    an extension to previously granted permission, planning registration reference 06/8591, for a 240 square metre two storey office structure to the east side of the existing manufacturing facility
  2. (b)
    the retention of a 107 square metre single storey timber framed structure within the loading bay area to the north
  3. (c)
    the construction of a 222 sq metre single storey extension to open roofed waste storage compound to the north west increasing the total area for the compound to 422 sq metres, the original compound was previously granted permission, planning registration reference 06/8591
  4. (d)
    the construction of a new 175 sq metre partially covered recycling area to the west of the site
  5. (e)
    the retention of a section of existing inner service link road to the east
  6. (f)
    the construction of 70 car spaces to the south; all with associated site works. All of the above facilities are ancillary to the existing production and plant areas located at DePuy (Ireland)
View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    9 Sept 2011

  2. Decision due

    3 Nov 2011

Application Details

Location
Depuy (Ireland) Loughbeg Ringaskiddy
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
9 September 2011
Status
INCOMPLETED APPLICATION
Decision
Pending
Decision Due
3 November 2011

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

15m
10/5581INCOMPLETED APPLICATION28 Jun 2010

Construction of extension of 2394sqm to the existing production & plant area & reconfiguration of the existing car park layout & associated site works

DePuy (Ireland) Ltd Loughbeg Ringaskiddy

16m
17/7095CONDITIONAL28 Nov 2017

The addition of 30 meters squared of glazing at first floor level to the western façade of the existing manufacturing facility

Loughbeg Ringaskiddy Co. Cork Co. Cork

18m
20/4200CONDITIONAL6 Feb 2020

a) The demolition of a 107 square metre single storey timber framed structure and cladded canopy within the loading bay area to the north of the existing production facility, b) the construction of 1 no. single storey extension within the loading bay area to the north and 1 no. single storey extension to the north west of the existing production facility and c) all associated modifications and site development works.

Loughbeg Ringaskiddy Co. Cork

35m
11/4944CONDITIONAL29 Apr 2011

Erection of 2 no. wind turbines with hub height of up to 100m, blade radius of up to 50.5m and overall height from ground to tip of blade of up to 150.5m, upgrade of existing site roads, construction of internal site tracks and all other associated works

Loughbeg Ringaskiddy Co Cork

51m
10/5662CONDITIONAL6 Jul 2010

Construction of a 2394 sq.m extension to the existing production & plant area & reconfiguration of existing carpark layout & associated site works

Loughbeg Ringaskiddy

51m
10/5142CONDITIONAL12 May 2010

Construction of new transformer building to rear of existing ESB sub-station and construction of new roof and cable gantry over the existing ESB sub-station and associated site works

DePuy Ireland Ltd Loughbeg Ringaskiddy

54m
11/6669CONDITIONAL21 Dec 2011

Construction of extension to western side of existing manufacturing facility (change of plan from that permitted under planning reg. no.10/5662) and minor reconfiguration of car park and associated site works at our manufacturing facility

Loughbeg Ringaskiddy

54m
11/6526INCOMPLETED APPLICATION2 Dec 2011

Amendments to previous permission for extension to the western side of the existing manufacturing facility granted under Pl. Reg. No.10/5662 to include alteration to West, North and South elevations of the extension; extending the ground floor by 3 metres in a westerly direction and introducting a new mezzanine level to part of the extension an increase of 1362 sq metres, bringing the total extension area to 3756 sq metres. The proposal requires minor reconfiguration of the carpark and associated site works

Loughbeg Ringaskiddy Co. Cork

54m
09/6961INCOMPLETED APPLICATION7 Sept 2009

Construction of new biomass boiler house incorporating a storage bunker

Loughbeg Ringaskiddy

54m
17/7090CONDITIONAL28 Nov 2017

Retention of a 107 square meter single storey timber framed structure for office use within the loading bay area to the north of the existing manufacturing facility. The above facility is ancillary to the existing production and plant areas.

Loughbeg Ringaskiddy Co. Cork

The submission window has closed

Observations on this application closed on Thursday 13 October 2011, five weeks after it was received. The authority cannot accept a late submission.