IDA Industrial Estate Barnagore Ovens Co. Cork
INCOMPLETED APPLICATIONPlanning application 12/6226
Cork - Cork County Council
Proposed Development
Construction of a new bus stop and shelter with widened concrete footpaths and associated civil and drainage works, a new personnel turnstile entrance, underground ducting to provide power for lighting for the shelter, and new road markings
View the full application file on the council's planning portal →Application Timeline
Application received
25 Oct 2012
Decision due
19 Dec 2012
Application Details
- Location
- IDA Industrial Estate Barnagore Ovens Co. Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 25 October 2012
- Status
- INCOMPLETED APPLICATION
- Decision
- Pending
- Decision Due
- 19 December 2012
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
New bus stop and shelter with widened concrete footpaths and associated civil & drainage works, a new personnel turnstile entrance and construction of an extension to the existing wall, underground ducting to provide power to the turnstile and lighting for the shelter, and new road markings
IDA Industrial Estate Barnagore Ovens Co.Cork
The construction of 25 No. dwellinghouses (change of plan of house No's 12 to 20 Codrum Lane , No's 14 to 31 Codrum Green). The proposed changes to above comprise of: a) The construction of 8 No. semi detached dwellings - denoted house no's 12-19 Codrum Lane, b) The construction of 16 No. semi detached and 1 No. detached dwellings - denoted house No's 14 to 30 Codrum Green, c) and all associated site works. The proposed development is a change plan from that originally permitted under Cork County Council Planning Ref : 06/12722 & ABP ref. PL 04.224953 and extended under ref 13/4725, 18/4980, 21/7517. This application will result in the re-designation of house address as outlined on the proposed site layout, there is an overall reduction of 2 dwelling units proposed as part of this planning application.
Codrum Hall Grange Ovens Co.Cork
The construction of a two-megawatt ballast-mounted photovoltaic panel array, associated electrical equipment and cabling on an area of grassland to the east of the main building on site. The array will have a maximum height of three metres above existing ground level, at the townland of Barnagore, Ovens, County Cork. This development is covered by the provisions of the Renewable Energy Directive III (Directive(EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply.
Barnagore, Ovens, County Cork, P31 D253
Planning permission for a new office building and data centre within the existing facility. The proposed development includes the construction of a 4 storey office building with an elevated atrium, a screened roof top plant area and roof top satellite dishes; a single storey data centre building with rooftop plant/air handling units; a 4 storey multi-storey car park with bicycle storage, dry room and staff locker rooms; the addition of a single storey deck to an existing car park; and all associated landscaping, fencing, signage and site development works. The proposed site development works include the relocation and replacement of the existing water tank and associated pumping station; the construction of 2 no. substations, an extension to and the re-cladding of the existing chiller block; an extension to and the re-cladding of the existing energy centre; the erection of a boiler flue; the installation of a pumping station and 8 no. generator units with 4 no. ancillary fuel tanks. Access to the proposed buildings will be via the existing access road and the proposed development includes modifications to the existing entrance arrangements. The proposed office building will be constructed in 2 phases over the period of the permission.
IDA Industrial Estate Barnagore Ovens
Permission for the construction of a 300-kilowatt ground-mounted photovoltaic panel array, associated electrical equipment and cabling on an area of existing hard-standing to the east of the main building on site. The array will have a maximum height of 3 metres above the existing ground level.
Barnagore Ovens Co. Cork
Completion and change of plan of house No.'s 25,26,27 Codrum Way. The proposed changes to above comprise of the following: a) the construction of a revised site entrance layout to provide for delegated car parking to house No.'s 25,26,27 Codrum Way, b) re-orientation of a play area to the common area c) all associated site works. The proposed development is a change of plan form that originally permitted under Pl.Reg.No. 06/12722 & ABP Ref. PL04.224953 and extended under Pl.Reg.No.'s 13/4725, 18/4980, 21/7517.
Codrum Hall Grange Ovens Co Cork
Full planning permission for the change of plan of house no.1 & no.2 Codrum Close, (House type E5) and all ancillary site works at Codrum Hall, Grange, Ovens, Co. Cork. The proposed development is a change of plan from that originally permitted under Cork County Council planning reference 06/12722 & ABP ref. PL04.224953 and extended under ref. 13/4725, 18/4980, 21/7517. This application will result in the redesignation of house address's as outlined on the proposed site layout, there are no additional units proposed as part of this planning application
Codrum Hall Grange Ovens Co.Cork
Demolition of existing dwellinghouse and storage shed, construction of residential development of 156 no. residential units comprising of 18 no. detached dwellings, 50 no. demi-detached dwellings, 80 no. terraced dwellings and 4 no. apartments, creche, 2 no. ESB sub-stations, foul water underground pumping station to include control building, new vehicular entrance and right hand turning lane and all associated site development works to include landscaping and the expansion of an existing waste water treatment plant on a separate site, extension of duration of permission granted under Planning Reg. No. 06/12722
Grange Ovens
Demolition of existing dwellinghouse and storage shed and construction of residential development of 156 no. residential units comprising of 18 no. detached dwellings, 50 no. semi-detached dwellings, 80 no. terraced dwellings and 4 no. apartments, creche, 2 no. ESB sub-stations, foul water underground pumping station to include control building, new vehicular entrance and right hand turning lane and all associated site development works to include landscaping and the expansion of an existing waste water treatment plant on a separate site. Extension of duration of permission granted under Planning Ref. 06/12722 and extended by 13/4725 and 18/4980 (Currently under consideration)
Codrum Hall Grange Ovens Co. Cork
Demolition of existing dwellinghouse and storage shed and construction of residential development of 161 no. residential units comprising of 18 no. detached dwellings, 52 no. semi-detached dwellings, 87 no. terraced dwellings and 4 no. apartments, creche, 2 no. ESB sub-stations, foul water underground pumping station to include control building, new vehicular entrance and right hand turning lane and all associated site development works to include landscaping and the expansion of an existing waste water treatment plant on a seperate site
Grange Ovens
Affected by this application?
Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.
Make a Submission or ObjectionPlanning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?