← Back to search

Brinny Innishannon Co. Cork

INCOMPLETED APPLICATION

Planning application 18/4483

Cork - Cork County Council

Proposed Development

The works include the construction of a new 2 storey extension with ground floor mezzanine to the east elevation of the existing Building 21(Planning ref:17/4830) The extension will comprise a freezer room, staging areas and the provision of roof mounted plant within the curtilage of a new parapet. The extension has a total floor area of 592 square meters and is 15.7 meters high. The works also include landscaping, underground and overground utilities, yards and associated siteworks. The works also include new external items of plant and equipment. This application consists of an activity for which an Industrial Emissions Licence under Part IV of the Environmental Protection Agency Act 1992 (as amended) is required.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    26 Feb 2018

  2. Decision due

    23 Apr 2018

Application Details

Location
Brinny Innishannon Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
26 February 2018
Status
INCOMPLETED APPLICATION
Decision
Pending
Decision Due
23 April 2018

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
18/4642CONDITIONAL15 Mar 2018

An extension to the existing Building 21 (Planning Ref. 17/4830) and associated works as follows: The works include the construction of a new 2 storey extension with ground floor mezzanine to the East elevation. The extension will comprise a freezer room, staging areas and the provision of roof mounted plant within the curtilage of a new parapet. The extension has a total floor area of 592 square metres and is 15.7 metres high. The works also include landscaping, underground and overground utilities, yards and associated siteworks. The works also include new external items of plant and equipment. The application consists of an activity for which an Industrial Emissions license under Part IV of the Environmental Protection Agency Act 1992 (as amended) is required.

Brinny Innishannon Co. Cork

39m
21/7034CONDITIONAL10 Nov 2021

The addition of a zinc box internally illuminated wind breaker with MSD logo to the entrance area of building 21 and associated site works along with the installation of a 2.43 metre high fence to the north site boundary of the building to tie into existing site fencing. This application relates to a development, which comprises an activity for which an Industrial Emissions License under part IV of the Environment Protection Agency Act 1992 (as amended) is required.

Brinny Innishannon Co. Cork

41m
21/5817CONDITIONAL30 Jun 2021

A waste collection area comprising an external yard, 4 no. waste storage units, plant for waste compaction, 1 no. canopy shelter, and all associated ancillary site works for the purpose of staging waste for regular collection at the facility. This application relates to a development, which comprises an activity for which an Industrial Emissions License under part IV of the Environment Protection Agency 1992 (as amended) is required.

Brinny Innishannon Co. Cork

50m
20/6297CONDITIONAL19 Oct 2020

A waste collection area consisting of external yard and 64sqm waste building for the purposes of staging waste for regular collection and associated ancillary site works. This application relates to a development, which comprises an activity for which an Industrial Emissions License under part IV of the Environment Protection Agency 1992 (as amended) is required.

Brinny Innishannon Co. Cork

62m
06/6127CONDITIONAL5 Apr 2006

Construction of single storey steel framed and cladded gas cylinder storage building

Brinny Innishannon

62m
06/4890INCOMPLETED APPLICATION17 Feb 2006

Construction of steel framed and cladded gas cylinder storage building

Brinny Innishannon

62m
07/5599INCOMPLETED APPLICATION2 Mar 2007

Construction of two storey extension and single storey extension to eastern elevation and two storey extension to Western elevation to OPS 2 Production building

Brinny Innishannon

62m
03/4178CONDITIONAL20 Aug 2003

Extension to fermentor building, to house contingency fermentor, link corridor & a 2 storey extension to utilities bay to service the fermentor

BRINNY, BRINNY,

62m
07/6860CONDITIONAL5 Apr 2007

Extensions to existing Operations 2 building to provide additional production, office and storage accommodation comprising of two storey extension and single storey extension to Eastern elevation and two storey extension to Western elevation

Brinny Innishannon

62m
04/8788CONDITIONAL30 Nov 2004

Demolition of a single storey solvent washroom annex to existing production building and construction of extension to house production plant

Brinny, Innishannon

Affected by this application?

Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.

Make a Submission or Objection

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?