← Back to search

Ballytrasna Little Island Co. Cork

CONDITIONAL

Planning application 20/5627

Cork - Cork County Council

Proposed Development

An extension to the existing production building, expansion of the site utility services, and provision of a new waste water treatment plant at this site. The proposed development will comprise of: (i) a three storey 1,723 sqm extension to a maximum height of 21.145m, including roof mounted equipment, to the north-west side of the existing single storey production building (maximum height of 9.35m), (ii) expansion of the utility yard to the west and north of the extension which will include; a chilled water system and buffer tanks, a clean-in-place system, a bunded diesel storage tank, a diesel generator and associated flue, a new boiler flue, a juice unloading bund, a 24 sqm single storey extension to the sprinkler pump house, and associated equipment access platforms and pipe racks (iii) a 118 sqm single storey chemical drum store lean-to enclosure (iv) a new waste water treatment plant, which will include c.1,856 sqm area of bunded tanks, a 165sqm single storey control building, a 64 sqm single storey electrical substation building, and a reconfigured access from the public road (v) the decommissioning and relocation of 40 No. existing car parking spaces from the existing R&D facility to a proposed extension to the car park (under construction) permitted under planning application reference 19/06776, and the addition of 13 No. new parking spaces (vi) temporary contractor’s compound, and (vii) all associated underground services, site development works and landscaping. The proposed development will also include the demolition and removal of redundant structures and equipment and the decommissioning of the existing waste water treatment plant. An Environmental Impact Assessment Report (EIAR) has been prepared and will be submitted to the Planning Authority with the application.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    30 Jul 2020

  2. Decision: CONDITIONAL

    20 Nov 2020

  3. Decision due

    2 Dec 2020

  4. Grant issued

    4 Jan 2021

Application Details

Location
Ballytrasna Little Island Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
30 July 2020
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
20 November 2020
Grant Date
4 January 2021

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

72m
09/5791CONDITIONAL2 Jun 2009

(1) Change of use of the existing maintenance store of the existing O'Neill's building to ground floor preparation area/tasting area & first floor office with external changes, (2) Change of use of existing R & D warehouse to part ground floor laboratory with associated offices overhead and external changes, and (3) Retention of existing E.S.B.substation at the existing PepsiCo Ireland Plant and associated works

Ballytrasna Little Island

73m
16/4332INCOMPLETED APPLICATION17 Feb 2016

The development will consist of the construction of a new plant room adjacent to the existing production building, comprising of a two storey steel frame with the steel cladding on the upper section. New floor area to be 143sq.m with an overall height not exceeding 10.513m

PepsiCo Worldwide Flavors Production Plant Little Island Industrial Estate, Ballytrasna Little Island Co. Cork

73m
16/4513CONDITIONAL7 Mar 2016

Construction of a new plant room adjacent to the existing production building, comprising of a two storey steel frame with the steel cladding on the upper section. New floor area to be 143sq.m with an overall height not exceeding 10.513m

PepsiCo Worldwide Flavors Production Little Island Industrial Estate Ballytrasna Little Island

77m
19/6640INCOMPLETED APPLICATION5 Nov 2019

Retention of development consists of a 510 sq.m single storey temporary offices and 130 car park spaces. Planning permission for development will consist of the following (i) a new detached 2 storey 252sq.m utility building to include ESB & electrical switch rooms at level 1 and control room, WC & MCC room on level 2 (ii) a detached single storey 63sq.m sprinkler pump house and associated sprinkler water storage tank (iii) 8 no. bunded external product storage tanks with a 250sq.m covered tanker unload facility and associated pipe rack (iv) the conversion of an existing covered external chemical storage area to an internal entrance area of 130sq.m to contain a new entry ramp (v) provision of 195 new additional car parking spaces (vi) re-positioning of 2 no. existing boundary gates and 1 new staff entrance gate which will include a covered walkway within the site boundary and all associated site development works for the above.

Ballytrasna Little Island Co. Cork

79m
19/6776CONDITIONAL21 Nov 2019

Retention of development consists of a 510 sq.m single storey temporary offices and 130 car park spaces. Planning permission for development will consist of the following (i) a new detached 2 storey 252sq.m utility building to include ESB & electrical switch rooms at level 1 and control room, WC & MCC room on level 2 (ii) a detached single storey 63sq.m sprinkler pump house and associated sprinkler water storage tank (iii) 8 no. bunded external product storage tanks with a 250sq.m covered tanker unload facility and associated pipe rack (iv) the conversion of an existing covered external chemical storage area to an internal entrance area of 130sq.m to contain a new entry ramp (v) provision of 195 new additional car parking spaces (vi) re-positioning of 2 no. existing boundary gates and 1 new staff entrance gate which will include a covered walkway within the site boundary and all associated site development works for the above.

Ballytrasna Little Island Co. Cork

82m
18/5047CONDITIONAL27 Apr 2018

Demolition of the existing Reagecon building including crushing concrete on site and all ancillary site works

Little Island Business Park Ballytrasna Little Island Co. Cork

97m
17/5900CONDITIONAL21 Jul 2017

Demolition of existing factory building, sub-station, chimney stack and associated sheds, including crushing conccrete on site and the construction of a new sub-station and switch room

Little Island Business Park Ballytrasna Little Island Co. Cork

97m
10/8189CONDITIONAL12 Oct 2010

Demolition of an existing industrial unit at north/west corner of site at Little Island Business Park and replacment of same with a surface level car park

Ballytrasna Little Island

99m
16/4667CONDITIONAL24 Mar 2016

Removal of the existing telecommunications equipment from chimney stack structure and the erection of a new 30m high multi-user telecommunications structure carrying associated antennae and link dishes and associated cabin and cabinets together with all ancillary site works

Little Island Industrial Estate Ballytrasna Little Island Co. Cork

105m
05/7103CONDITIONAL30 Sept 2005

Construction of single storey self contained warehouse with loading docks for storage of finished concentrate for soft drinks, attached two storey unit with switch room and fork truck maintenance areas on ground floor and offices on first floor, covered link to existing warehouse on adjoining site, security hut, installation of fire water retention pond, removal of existing pond, installation of attenuation tank, entrance and ancillary site works

Ballytrasna Little Island

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?