← Back to search

Annagh North Near Churchtown Co. Cork

INCOMPLETED APPLICATION

Planning application 21/4991

Cork - Cork County Council

Proposed Development

Permission for retention for the continued use of an existing temporary lattice type meteorological mast, 80m in height. The structure is fixed to ground mounted anchors by guy wires and includes associated instruments to measure local meteorological conditions. Permission for retention is sought for a period of 5 years. (The mast was erected on site as exempted development pursuant to Class 20 (A), Part 1, Schedule 2 of the Planning & Development Regulations 2001 (as amended) in July, 2019).

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    16 Apr 2021

  2. Decision due

    10 Jun 2021

Application Details

Location
Annagh North Near Churchtown Co. Cork
Applicant
N/A
Application Type
RETENTION
Planning Authority
Cork County Council

Timeline

Registration Date
16 April 2021Other applications received that week
Status
INCOMPLETED APPLICATION
Decision
Pending
Decision Due
10 June 2021

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

560m
21/7246Refused3 Dec 2021

The development will consist of: . Construction of 6 no. wind turbines with a blade tip height of 175m, rotor diameter of 150m and a hub height of 100m; . Construction of turbine foundations and crane pad hardstanding areas; . Construction of new site tracks and associated drainage infrastructure; . Upgrading of existing tracks and associated drainage infrastructure where necessary; . Upgrade of entrance onto local road L1322; . All associated drainage and sediment control including the installation of new watercourse or drain crossing and the re-use or upgrading of existing internal watercourse and drain crossings; . Construction of 1 no. permanent onsite 38kV electrical substation to ESBN specifications including: - Control building with welfare facilities; - Electrical infrastructure; - Parking; - Wastewater holding tank; - Rainwater harvesting; - Security fencing; - All associated infrastructure, services and site works. . 1 no temporary construction site compound and associated ancillary infrastructure including parking; . Tree felling to facilitate construction and operation of the proposed development; . Installation of medium voltage (20/33kV) and communication underground cabling between the proposed turbines and the proposed on-site substation and associated ancillary works; . Erection of 1 no. permanent meteorological mast with a height of 100m above ground level and associated access track; . Installation of medium voltage (38kV) underground cabling and associated ancillary works between the proposed on-site substation and the existing Charleville Substation within the townland of Rathnacally. The proposed grid connection will be installed primarily within the public road and will include 2 no. watercourse crossings and the installation of 8 no. pre-cast joint bays; . All associated site development works; . A 10 planning permission and 35 year operational life from the date of commissioning of the entire wind farm. This application for planning permission is accompanied by an Environmental Impact Assessment Report and Natura Impact Statement.

Annagh North, Coolcaum, Fiddane Cooliney, Rathnacally, Farranshonikeen Ardnageehy and Clashganniv Co. Cork

862m
19/6816INCOMPLETED APPLICATION25 Nov 2019

The development of a 67.8 hectare solar PV farm. The proposed solar farm will consist of the installation of a 40 year operation and subsequent decommissioning of a series of ground mounted solar photovoltaic (PV) panels, mounted on steel support structures 2.1m in height, together with 1 single storey ESB control room, 9 electrical transformation enclosures, underground cabling, CCTV poles and cameras, deer type security fencing, site entrance, hardstanding area, landscaping along part of the northern site boundary and other associated development works, for the purpose of generating renewable energy electricity. A Natura Impact Statement will be submitted to the planning authority with this application.

Fiddane Townland Ballyhea Charleville Co. Cork

864m
17/5799CONDITIONAL13 Jul 2017

Development of a 67.8 hectare Solar PV Farm. The proposed solar farm will consist of the installation of a 30 year operation and subsequent decommissioning of a series of ground mounted solar photovoltaic (PV) panels, mounted on steel support structures 2.1m in height, together with 1 single storey ESB control room, 14 electrical transformation enclosures, underground cabling, CCTV poles and cameras, deer type security fencing, site entrance, hardstanding area, landscaping along part of the northern site boundary and other associated development works, for the purpose of generating renewable energy electricity.

Fiddane Ballyhea Co. Cork Co. Cork

865m
22/6536CONDITIONAL14 Nov 2022

Permission to amend the design of the previously approved development (planning reference: Cork County Council 17/5799 & an Bord Pleanála ABP-306915-20)which comprises consent for a 67.8 hectare Solar PV farm at Fiddane, Ballyhea Charleville, Co.Cork. The proposed amendments include; (1) increase in number of transformers, (2) reduction in the spacing of Solar PV rows (strings), (3) increase in size and configuration of solar panels, (4) overall increase in solar power generation, (5) change in solar panels tilt (degree), (6) minor reduction in the height of solar array, (7) operational period proposed to be extended from 30 to 40 years. A Natura Impact Statement will be submitted to the planning authority with this application.

Fiddane Ballyhea Charleville Co.Cork

865m
19/6965WITHDRAWN13 Dec 2019

The development of a 67.8 hectare solar PV farm. The proposed solar farm will consist of the installation of a 40 year operation and subsequent decommissioning of a series of ground mounted solar photovoltaic (PV) panels, mounted on steel support structures 2.1m in height, together with 1 single storey ESB control room, 9 electrical transformation enclosures, underground cabling, CCTV poles and cameras, deer type security fencing, site entrance, hardstanding area, landscaping along part of the northern site boundary and other associated development works, for the purpose of generating renewable energy electricity. A Natura Impact Statement will be submitted to the planning authority with this application.

Fiddane Townland Ballyhea Charleville Co. Cork

1.1km
07/4536CONDITIONAL29 Jan 2007

Construction of waste water treatment storage tank, livestock unit to include cubicles, slatted area, slatted slurry storage tanks, feeding passage and collection yard

Annagh South Churchtown Mallow

1.1km
07/8891CONDITIONAL21 Jun 2007

Construction of overground slurry tank, slatted reception tank and slatted emptying tank

Annagh South Churchtown Mallow

1.2km
05/7805CONDITIONAL25 Oct 2005

Dwelling and garage

Annagh South Churchtown Mallow

1.2km
26/1323Awaiting F.I. Response19 May 2026

Permission for retention of the revised site boundaries and associated site development works, as revised from that previously permitted under planning reference: 05/7805.

Annagh South, Churchtown, Mallow. Co. Cork. P51 F30A

1.2km
06/4725CONDITIONAL13 Feb 2006

Domestic garage and relocation of entrance to dwellinghouse

Annagh North Churchtown

The submission window has closed

Observations on this application closed on Thursday 20 May 2021, five weeks after it was received. The authority cannot accept a late submission.

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?