Annagh North, Coolcaum, Fiddane Cooliney, Rathnacally, Farranshonikeen Ardnageehy and Clashganniv Co. Cork
RefusedPlanning application 21/7246
Cork - Cork County Council
Proposed Development
The development will consist of: . Construction of 6 no. wind turbines with a blade tip height of 175m, rotor diameter of 150m and a hub height of 100m; . Construction of turbine foundations and crane pad hardstanding areas; . Construction of new site tracks and associated drainage infrastructure; . Upgrading of existing tracks and associated drainage infrastructure where necessary; . Upgrade of entrance onto local road L1322; . All associated drainage and sediment control including the installation of new watercourse or drain crossing and the re-use or upgrading of existing internal watercourse and drain crossings; . Construction of 1 no. permanent onsite 38kV electrical substation to ESBN specifications including: - Control building with welfare facilities; - Electrical infrastructure; - Parking; - Wastewater holding tank; - Rainwater harvesting; - Security fencing; - All associated infrastructure, services and site works. . 1 no temporary construction site compound and associated ancillary infrastructure including parking; . Tree felling to facilitate construction and operation of the proposed development; . Installation of medium voltage (20/33kV) and communication underground cabling between the proposed turbines and the proposed on-site substation and associated ancillary works; . Erection of 1 no. permanent meteorological mast with a height of 100m above ground level and associated access track; . Installation of medium voltage (38kV) underground cabling and associated ancillary works between the proposed on-site substation and the existing Charleville Substation within the townland of Rathnacally. The proposed grid connection will be installed primarily within the public road and will include 2 no. watercourse crossings and the installation of 8 no. pre-cast joint bays; . All associated site development works; . A 10 planning permission and 35 year operational life from the date of commissioning of the entire wind farm. This application for planning permission is accompanied by an Environmental Impact Assessment Report and Natura Impact Statement.
Application Timeline
Application received
3 Dec 2021
Decision: Refused
22 Dec 2022
Decision due
6 Jan 2023
Application Details
- Location
- Annagh North, Coolcaum, Fiddane Cooliney, Rathnacally, Farranshonikeen Ardnageehy and Clashganniv Co. Cork
- Applicant
- N/A
- Application Type
- Permission
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 3 December 2021Other applications received that week
- Status
- Appeal lodged
- Decision
- Refused
- Decision Date
- 22 December 2022
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Permission for retention for the continued use of an existing temporary lattice type meteorological mast, 80m in height. The structure is fixed to ground mounted anchors by guy wires and includes associated instruments to measure local meteorological conditions. Permission for retention is sought for a period of 5 years. (The mast was erected on site as exempted development pursuant to Class 20 (A), Part 1, Schedule 2 of the Planning & Development Regulations 2001 (as amended) in July, 2019).
Annagh North Near Churchtown Co. Cork
The development of a 67.8 hectare solar PV farm. The proposed solar farm will consist of the installation of a 40 year operation and subsequent decommissioning of a series of ground mounted solar photovoltaic (PV) panels, mounted on steel support structures 2.1m in height, together with 1 single storey ESB control room, 9 electrical transformation enclosures, underground cabling, CCTV poles and cameras, deer type security fencing, site entrance, hardstanding area, landscaping along part of the northern site boundary and other associated development works, for the purpose of generating renewable energy electricity. A Natura Impact Statement will be submitted to the planning authority with this application.
Fiddane Townland Ballyhea Charleville Co. Cork
Development of a 67.8 hectare Solar PV Farm. The proposed solar farm will consist of the installation of a 30 year operation and subsequent decommissioning of a series of ground mounted solar photovoltaic (PV) panels, mounted on steel support structures 2.1m in height, together with 1 single storey ESB control room, 14 electrical transformation enclosures, underground cabling, CCTV poles and cameras, deer type security fencing, site entrance, hardstanding area, landscaping along part of the northern site boundary and other associated development works, for the purpose of generating renewable energy electricity.
Fiddane Ballyhea Co. Cork Co. Cork
Permission to amend the design of the previously approved development (planning reference: Cork County Council 17/5799 & an Bord Pleanála ABP-306915-20)which comprises consent for a 67.8 hectare Solar PV farm at Fiddane, Ballyhea Charleville, Co.Cork. The proposed amendments include; (1) increase in number of transformers, (2) reduction in the spacing of Solar PV rows (strings), (3) increase in size and configuration of solar panels, (4) overall increase in solar power generation, (5) change in solar panels tilt (degree), (6) minor reduction in the height of solar array, (7) operational period proposed to be extended from 30 to 40 years. A Natura Impact Statement will be submitted to the planning authority with this application.
Fiddane Ballyhea Charleville Co.Cork
The development of a 67.8 hectare solar PV farm. The proposed solar farm will consist of the installation of a 40 year operation and subsequent decommissioning of a series of ground mounted solar photovoltaic (PV) panels, mounted on steel support structures 2.1m in height, together with 1 single storey ESB control room, 9 electrical transformation enclosures, underground cabling, CCTV poles and cameras, deer type security fencing, site entrance, hardstanding area, landscaping along part of the northern site boundary and other associated development works, for the purpose of generating renewable energy electricity. A Natura Impact Statement will be submitted to the planning authority with this application.
Fiddane Townland Ballyhea Charleville Co. Cork
The installation of two 33kV electricity grid interconnectors with a combined total length of 2,217m of underground cable with a joint bay and 1,146m of over head line supported by 8 triple pole sets and 5 double pole sets, a temporary construction compound and 4 transformer stations. The proposed development is to connect the permitted but not built solar farm development at Fiddane (pl.ref 17/05799 & ABP-308846-20) to the consented but not built Ballyroe solar farm (pl/ref. 20/04041), co.Cork and the proposed solar farm development at Coolcaum to the consented but not built Ballyroe solar farm (pl.Ref 20/04041), co.Cork. The cables will be under public road and private lands. The location of the proposed development is in the townlands of Fiddane, Cooliney, Ballynoran, Coolcaum, and Ballyroe near Charleville. A Natura Impact Statement will be submitted to the planning authority with this application.
The Townlands of Fiddane, Cooliney, Ballynoran, Coolcaum & Ballyroe, Charleville, Co.Cork.
The installation of two 33kV electricity grid interconnectors with a combined total length of 2,217m of underground cable with a joint bay and 1,146m of overhead line supported by 8 triple pole sets and 5 double pole sets, a temporary construction compound and two transformer stations. The proposed development is to connect the permitted but not built solar farm development at Fiddane (Pl. Ref. 17/05799 & ABP-308846-20) to the consented but not built Ballyroe Solar Farm (Pl. Ref. 20/04041), Co. Cork and the proposed solar farm development at Coolcaum to the consented but not built Ballyroe Solar Farm (Pl. Ref. 20/04041), Co. Cork. The cables will be under public road and private lands. A Natura Impact Statement will be submitted to the Planning Authority with this application.
Fiddane, Cooliney, Ballynoran, Coolcaum Ballyroe, Charleville Co. Cork
Construction of cubicle house, slurry tank, silage slab and associated site works including effluent tank
Cooliney Charleville
Construction of soiled water/effluent storage tank and walled silage pit with concrete apron.
Cooliney Ballyhea Co. Cork
Permission to (a) demolish a rear single storey extension, chimneys and rear dormer type window of the existing dwelling house, (b) demolish an existing rear single storey storage type building, (c) Permission to construct a two storey rear extension and a single storey link section and alterations to the existing dwelling house and (d) Permission to install a wastewater treatment plant and soil polishing filter and all associated site works.
Fiddane, Charleville, Co. Cork, P56 NC84.