Beaufort Building - Environmental Research Institute, University College Cork Haubowline Road Loughbeg Ringaskiddy, Co. Cork
CONDITIONALPlanning application 21/7291
Cork - Cork County Council
Proposed Development
The removal of 8 no. car parking spaces permitted under Cork County Council planning application 11/5487, and their replacement with the construction of an open-air outdoor enclosure comprising of a concrete base, timber panel security fence and access gateways, fixed to the existing in-situ concrete wall, and all associated development. The enclosure will house a test rig, consisting of pipe work,3 no. water tanks, and electronic equipment, mounted on a steel framed platform (a skid) to facilitate transport by road and ease of installation and allow for the removal of the rig once testing is complete after approximately 3 years.
Application Timeline
Application received
9 Dec 2021
Decision: CONDITIONAL
9 Feb 2022
Decision due
11 Feb 2022
Grant issued
24 Mar 2022
Application Details
- Location
- Beaufort Building - Environmental Research Institute, University College Cork Haubowline Road Loughbeg Ringaskiddy, Co. Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 9 December 2021Other applications received that week
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 9 February 2022
- Grant Date
- 24 March 2022
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Removal of three car parking spaces and the erection of a research container unit.
Beaufort Building - Environmental Research Institute University College Cork Haulbowline Road Loughbeg Ringaskiddy Co Cork
Permission for the relocation and erection of a small micro generation research wind turbine at the north -eastern corner of the site. The wind turbine will be used to provide power to the Beaufort Building and for the educational purposes. The project involves: 1) construction of a concrete foundation for the turbine (measuring 12.25m2), 2) erection of the tower and turbine (metal lattice tower and turbine with tip height of 19.1m) and 3) associated site works, fencing and utility connections
Beaufort Building - Environmental Research University College Cork, Haulbowline Road Loughbeg, Ringaskiddy Co.Cork
Widening of existing entrance, relocation of existing front road boundary fence, relocation of weighbridge, change of use of building 1 & 2 from bulk storage of granulated fertilizer to accommodate port related activities including storage and screening of wood pellets, timber, feedstuffs and non hazardous fertilizers routed through Port of Cork and open storage of finished product on pallets
Ringaskiddy
Widening of existing entrance, relocation of existing front road boundary fence, relocation of weighbridge, change of use of Building No's 1 & 2 to accommodate port related activities to include storage and screening of wood pellets, timber, feedstuffs and non hazardous fertilizers routed through Port of Cork and open sotrage of finished product on pallets
Ringaskiddy
Change of use of existing dis-used loading yard area to use for the open storage of aggregate material for road re-surfacing and use of existing hardcore yard for occasional re-cycling of aggregate material using mobile cold bitumen recycling mixing equipment
Ringaskiddy Co. Cork .
For the change of use of existing dis-used loading yard area to use for the open storage of aggregate material for road re-surfacing and use of existing hardcore yard for occasional re-cycling of aggregate material using mobile mixing equipment
Ringaskiddy Co.Cork .
Conversion of industrial storage facility in a former magazine building to crematorium with associated site works
Rocky Island Ringaskiddy
a) The demolition of a 107 square metre single storey timber framed structure and cladded canopy within the loading bay area to the north of the existing production facility, b) the construction of 1 no. single storey extension within the loading bay area to the north and 1 no. single storey extension to the north west of the existing production facility and c) all associated modifications and site development works.
Loughbeg Ringaskiddy Co. Cork
Retention of a 240 square meter two storey structure for office use on the east side of the existing manufacturing facility. The above facility is ancillary to the existing production and plant areas
Loughbeg Ringaskiddy Co. Cork
Retention of a 60metre high meteorological data collection mast at Loughbeg. The period of retention in relation to this application is 2 years
Loughbeg Industrial Estate Loughbeg Ringaskiddy
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?