The proposed 3no. underground cable routes, or sections of cable routes in Dublin City are located in the Ashtown, Glasnevin and North Wall areas as follows:, The proposed Coolmine cable route section connecting the permitted Ashtown 38 kV substation (AC
ADDITIONAL INFORMATIONPlanning application WEB1097/26
Dublin - Dublin City Council
Proposed Development
The Electricity Supply Board (ESB) intends to apply for permission for a 10-year approval for development at this site consisting of up to approximately 3.72 kilometres (km) of 38 kilovolts (kV) underground cable (UGC) across 3 no. routes at different locations in Dublin City with a total site area of c.4.23ha. The proposed UGC are located at the Ashtown, Glasnevin and North Wall areas within Dublin City. The proposed development consists of the following elements: • Installation of 3no. new 38 kV underground cable routes, or cable route sections, and all associated site and development works within the administrative area of Dublin City Council (DCC) as outlined below and illustrated on the maps herein: - The proposed Coolmine cable route section within DCC is approximately 1.14km in length connecting the permitted Ashtown 38 kV substation (ACP Ref. 314232) to the County Border with Fingal at Navan Road (R147). - The proposed Glasnevin cable route is wholly within DCC and is approximately 1.2km in length connecting the existing Glasnevin 38kV substation to the permitted Clareville 38kV substation (ACP Ref. 314232). - The proposed North Quays cable route is wholly within DCC and is approximately 1.38km in length connecting the permitted Spencer Dock 38kV substation (ACP Ref. 314232) with the existing 38 kV circuit on East Wall Road (R131). The primary purpose of the proposed underground cables is to provide electrical power to the Dart+ West Railway project as granted under the DART+ West Railway Order (ACP Ref. 314232). The proposed underground cable routes will incorporate the following elements: • Communication links and fibre optic cables between all substations in the same trench as the UGC; • Joint bays and communication chambers along the UGC alignment; • Temporary construction laydown and work areas with ancillary staff facilities and parking, temporary access tracks, passing bays and water and utility crossings. • All associated and ancillary above and below ground site development works, including works comprising or relating to permanent and temporary construction and roadworks and excavation (including HDD) and vegetation clearance. Refer to the enclosed site and newspaper notices for a full description of development for the maps attached.
Application Timeline
Application received
16 Jan 2026
Further information requested
11 Mar 2026
Decision: ADDITIONAL INFORMATION
11 Mar 2026
Decision due
12 Mar 2026
Application Details
- Location
- The proposed 3no. underground cable routes, or sections of cable routes in Dublin City are located in the Ashtown, Glasnevin and North Wall areas as follows:, The proposed Coolmine cable route section connecting the permitted Ashtown 38 kV substation (AC
- Applicant
- N/A
- Application Type
- Permission
- Planning Authority
- Dublin City Council
- Site Area
- 48121.05 ha
Timeline
- Registration Date
- 16 January 2026
- Status
- Decision Notice Issued
- Decision
- ADDITIONAL INFORMATION
- Decision Date
- 11 March 2026
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
The development will consist of variations to previously approved permission Register Ref. No. 3951/18 to include the following: (a) First floor extension to provide for ancillary storage in lieu of previously approved basement which is to be omitted from the development and (b) associated elevation alterations.
The Halfway House, Navan Road, Ashtown, Dublin 7
Planning permission is sought to carry out a development at The Halfway House, Navan Road, Ashtown, Dublin 7 involving a) change of use of the existing first floor area (346sq.m) from storage and staff facilities to use as a guesthouse with staff facilities, b) to construct an extension of 478sq.m at first floor level for use as part of a guesthouse. The entire first floor level as extended to be used as part of this new facility will comprise 18 self catering guest rooms, foyer, storage and all other ancillary works. The proposed development will include an extension of 34sq.m at ground floor level to facilitate the relocation of the existing ground floor toilets and the demolition of a single storey ground floor store of 21 sq.m, the extension of the existing external terrace and the associated elevation alterations arising from the development.
The Halfway House, Navan Road, Ashtown, Dublin 7
Planning permission is sought to carry out a development at the Halfway House, Navan Road, Ashtown, Dublin 7 involving a) change of use of the existing first floor area (346sq.m) from storage and staff facilities to use as a standard guesthouse with staff facilities; (b) to construct an extension of 476sq.m at first floor level for use as part of a guesthouse. The entire first floor level as extended to be used as part of this new facility will comprise 24 standard guest rooms, foyer, storage and all other ancillary works. The proposed development will include an extension of 34sq.m at ground floor level to facilitate the relocation of the existing ground floor toilets and the demolition of a single storey ground floor store of 21 sq.m, the extension of the existing external terrace and the associated elevation alterations arising from the development.
The Halfway House, Navan Road, Ashtown, Dublin 7
Retention permission for the development consists of the retention of a modified shipping container, 6m x 2.44m, located within the existing car park, to be used as a facility for serving to go coffee and snacks during the hours of 7am to 7pm Monday to Sunday. The development to be retained results in the omission of 4 no. existing cark parking spaces.
The Halfway House, Navan Road, Dublin 7
a) the provision of a dormer window to the rear for an existing converted attic. b) Single storey porch and canopy extension to the front c) New roof window to the rear All with ancillary site works
7, Martin Savage Park, Ashtown, Dublin 15
Planning permission is sought for alteration/extension of the existing two storey semi-detached house comprising construction of a new single storey extension to the rear, a new 2-storey pitched roof extension to the side with 2 no. Velux rooflights to the rear roof slope, conversion of the attic space including 2 no. dormer windows to the rear roof slope and 3 no. Velux rooflights to the front, and construction of a new two storey porch extension to the front with associated site development.
383, Navan Road, Ashtown, Dublin 7, D07 VNY3
Permission for the demolition of 'Arnott House'
'Arnott House', Located at the former Phoenix Park Racecourse at the,
New for development consisting of construction of a new, detached three storey, 4 bedroomed house to side garden of existing dwelling (no.8), including retaining existing vehicular entrance; raising of front boundary wall to 1.8m and all associated site works; and for works to existing house (no.8) to include the provision of a new vehicular entrance and driveway to front garden, a new 16m2 single storey rear extension, internal alterations and all associated site works
8 & 8a Martin Savage Park, Navan Road, Ashtown, Dublin 15
Development consisting of construction of a new, detached three storey, 4 bedroomed house to side garden of existing dwelling, including retaining existing vehicular entrance; raising of side/front boundary wall to 1.8m and all associated site works; and for works to existing house to include the provision of a new vehicular entrance and driveway to front garden, a new 16m2 single storey rear extension, internal alterations and all associated site works
8, Martin Savage Park, Navan Road, Ashtown, Dublin 15
For development consisting of construction of a new, detached three storey, 4 bedroomed house to side garden of existing dwelling, including retaining existing vehicular entrance; raising of front boundary wall to 1.8m and all associated site works; and for works to existing house to include the provision of a new vehicular entrance and driveway to front garden, a new 16m2 single storey rear extension, internal alterations and all associated site works.
8, Martin Savage Park, Navan Road, Ashtown, Dublin 15