(a) Increase existing 2.4m railings to front boundary to 3.1m high; (b) increase existing 2.4m high palisade fencing to east & south boundaries to 3.1m high
View the full application file on the council's planning portal →Application Timeline
Application received
9 Aug 2016
Decision: Declared Not Exempt
1 Sept 2016
Decision due
5 Sept 2016
Application Details
- Location
- Dub 53, Greenhills Road, Tallaght, Dublin, 24
- Applicant
- N/A
- Application Type
- Declaration of Exemption Sect. 5
- Planning Authority
- South Dublin County Council
- Site Area
- 78.1411539818814 ha
Timeline
- Registration Date
- 9 August 2016
- Status
- Decision
- Decision
- Declared Not Exempt
- Decision Date
- 1 September 2016
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Upgrade of the existing boundary railings and palisade fence by increasing the height of the existing fencing and railings by 0.7 meters to the overall site boundary.
DUB 53, Greenhills Road, Tallaght, Dublin, 24
Retention of alterations to previously granted planning permission, Reg. Ref. SD14A/0232: (1) Modification to the site entrance arrangement at the north boundary, including the omission of the security hut and the redesign of gates; (2) redesign of the sprinkler water tank and pump house compound; (3) relocation of the humidifier pump house and tanks to the south eastern corner of the main building, with the redesigned tank room enclosed within the main building; (4) rearrangement of the stand by generators layout; (5) relocation of the temporary substation to the south western corner of the main building; (6) new enclosure to stand-by generators; (7) rearrangement of the accessible parking spaces; (8) 164sq.m of added circulation, loading and storage accommodation at ground floor level and 9sq.m at mezzanine level; (9) changes to the main building to facilitate access to the relocated loading bay; (10) internal layout changes to offices and west storage bay areas with associated elevational changes; (11) 79sq.m of additional accommodation at first floor level with associated elevational changes; and (12) enlargement of louvered wall vents on the south elevation. The total added accommodation equals 252sq.m.
Former Shinko Microelectronics Site, Greenhills Business Park, Greenhills Road, Tallaght, Dublin 24.
Upgrade existing tertiary site entrance including the replacement of the existing gate.
Greenhills Centre, Greenhills Road, Tallaght, Dublin 24.
To upgrade existing nitrogen tank from 12 metres high x 2.35 metres diameter to 12 metres high x 2.85 metres diameter at their premsies at Greenhills Centre, Greenhills Road, Dublin 24.
Shinko Microelectronics, Greenhills Center, Greenhills Road Tallaght, Dublin 24
Construction of a new two storey c.11,700sq.m building for use as electrical rooms for electronic operations, mechanical plant rooms and support areas including a loading bay, offices and welfare facilities; mechanical plant at roof level is screened from view on all sides; a new 50sq.m electrical substation; a new plant array along the east site boundary including an electrical substation transformer compound; a 90sq.m electrical substation control room; a diesel fuel tank farm and loading bay; a 10sq.m fuel pump house; a sprinkler water tank; a 70sq.m water pump house; a humidifier water tank farm; the repositioning and widening of vehicular entrances; 2 site entrances at changed locations in place of 3 existing; 23 car parking spaces, landscaping and ancillary works; the combined gross floor area of the proposed buildings totals c. 11,920sq.m; demolition of existing buildings is being carried out under grant of permission Reg. Ref. SD13A/0266.
Former Shinko Building, Greenhills Road, Tallaght, Dublin 24
Demolition of the existing industrial building and ancillary structures on the site.
Former Shinko Building, Greenhills Road, Tallaght, Dublin 24
Construction of a new 2 storey building (c.8229sq.m) for use as a data storage facility. The new facility will be an annex to, and accessed through, the neighbouring data storage facility to the north via the existing site entrance serving same. The development will include electrical rooms for electronic operations, mechanical plant rooms and support areas including offices and welfare facilities, a loading bay and back-up generators in a fenced compound. Existing boundary structures including railings, fencing and gates will be replaced with a new 3, high perimeter railing. Ventilation plant at roof level will be screened from view on all sides (all at the former Barretts site).
Greenhills Business Park, Greenhills Road, Dublin 24
The development consists of the retention of existing 60 sq. m. of additional first floor offices within Unit 13.
Unit 13, Greenhills Business Centre, Hibernian Industrial Estate, Greenhills Road, Dublin 24, D24N673
Retention sought for internal mezzanine store and modifications.
8 Greenhills Business Centre, Greenhills Road, Dublin 24.
The development will comprise: (1) The Installation of 2 no. new Air Handling Units & associated ducts externally to the existing south façade in place of the previously permitted ( Planning Permission SD13A/0266) generator units. (2) External alterations to existing south façade to incorporate flashings to new wall penetrations. (3) Construction of perimeter fence as per previously permitted (Planning Reference SD17A/0448). (4) Associated site works to perimeter road in order to provide safe pedestrian access & Crossings
Former Shinko Microelectronics Site, Greenhills Business Park, Greenhills Road, Tallaght, Dublin 24.
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?