DUB 53, Greenhills Road, Tallaght, Dublin, 24
GrantedPlanning application SD16A/0427
Dublin - South Dublin County Council
Proposed Development
Upgrade of the existing boundary railings and palisade fence by increasing the height of the existing fencing and railings by 0.7 meters to the overall site boundary.
View the full application file on the council's planning portal →Application Timeline
Application received
9 Dec 2016
Decision: Grant Permission
1 Feb 2017
Decision due
13 Feb 2017
Grant issued
14 Mar 2017
Application Details
- Location
- DUB 53, Greenhills Road, Tallaght, Dublin, 24
- Applicant
- N/A
- Application Type
- Permission
- Planning Authority
- South Dublin County Council
- Site Area
- 17400 ha
Timeline
- Registration Date
- 9 December 2016
- Status
- Decision
- Decision
- Grant Permission
- Decision Date
- 1 February 2017
- Grant Date
- 14 March 2017
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Retention of alterations to previously granted planning permission, Reg. Ref. SD14A/0232: (1) Modification to the site entrance arrangement at the north boundary, including the omission of the security hut and the redesign of gates; (2) redesign of the sprinkler water tank and pump house compound; (3) relocation of the humidifier pump house and tanks to the south eastern corner of the main building, with the redesigned tank room enclosed within the main building; (4) rearrangement of the stand by generators layout; (5) relocation of the temporary substation to the south western corner of the main building; (6) new enclosure to stand-by generators; (7) rearrangement of the accessible parking spaces; (8) 164sq.m of added circulation, loading and storage accommodation at ground floor level and 9sq.m at mezzanine level; (9) changes to the main building to facilitate access to the relocated loading bay; (10) internal layout changes to offices and west storage bay areas with associated elevational changes; (11) 79sq.m of additional accommodation at first floor level with associated elevational changes; and (12) enlargement of louvered wall vents on the south elevation. The total added accommodation equals 252sq.m.
Former Shinko Microelectronics Site, Greenhills Business Park, Greenhills Road, Tallaght, Dublin 24.
Upgrade existing tertiary site entrance including the replacement of the existing gate.
Greenhills Centre, Greenhills Road, Tallaght, Dublin 24.
To upgrade existing nitrogen tank from 12 metres high x 2.35 metres diameter to 12 metres high x 2.85 metres diameter at their premsies at Greenhills Centre, Greenhills Road, Dublin 24.
Shinko Microelectronics, Greenhills Center, Greenhills Road Tallaght, Dublin 24
Construction of a new two storey c.11,700sq.m building for use as electrical rooms for electronic operations, mechanical plant rooms and support areas including a loading bay, offices and welfare facilities; mechanical plant at roof level is screened from view on all sides; a new 50sq.m electrical substation; a new plant array along the east site boundary including an electrical substation transformer compound; a 90sq.m electrical substation control room; a diesel fuel tank farm and loading bay; a 10sq.m fuel pump house; a sprinkler water tank; a 70sq.m water pump house; a humidifier water tank farm; the repositioning and widening of vehicular entrances; 2 site entrances at changed locations in place of 3 existing; 23 car parking spaces, landscaping and ancillary works; the combined gross floor area of the proposed buildings totals c. 11,920sq.m; demolition of existing buildings is being carried out under grant of permission Reg. Ref. SD13A/0266.
Former Shinko Building, Greenhills Road, Tallaght, Dublin 24
Demolition of the existing industrial building and ancillary structures on the site.
Former Shinko Building, Greenhills Road, Tallaght, Dublin 24
(a) Increase existing 2.4m railings to front boundary to 3.1m high; (b) increase existing 2.4m high palisade fencing to east & south boundaries to 3.1m high
Dub 53, Greenhills Road, Tallaght, Dublin, 24
Construction of a new 2 storey building (c.8229sq.m) for use as a data storage facility. The new facility will be an annex to, and accessed through, the neighbouring data storage facility to the north via the existing site entrance serving same. The development will include electrical rooms for electronic operations, mechanical plant rooms and support areas including offices and welfare facilities, a loading bay and back-up generators in a fenced compound. Existing boundary structures including railings, fencing and gates will be replaced with a new 3, high perimeter railing. Ventilation plant at roof level will be screened from view on all sides (all at the former Barretts site).
Greenhills Business Park, Greenhills Road, Dublin 24
The modification of the site entrance on the northern boundary, including the replacement of the existing gates with new wider gates and associated changes to the carriageway and perimeter security fencing. The construction of a new, single storey security building and the construction of a new vehicular security enclosure with new security fencing and a second set of matching inner gates. The rearrangement of the two existing accessible parking spaces and the relocation of 7 car parking spaces to the southern boundary of the site, retaining 24 car parking spaces on the site overall as per PP SD17A/0448. Relocating the existing bicycle shelter and all associated ancillary site works. The total area of the proposed new security building is 50.75 sqm.
Former Shinko Microelectronics Site, Greenhills Business Park, Greenhills Road, Tallaght, D24 HY58
Provision of a single storey cafe unit with associated signage, new pedestrian entrance with associated gates, walls and railings; utilisation of existing vehicular entrance from Greenhills Road, along with all associated site and engineering development works necessary to facilitate the development.
Greenhills Centre, Greenhills Road, Tallaght, Dublin 24.
The development consists of the retention of existing 60 sq. m. of additional first floor offices within Unit 13.
Unit 13, Greenhills Business Centre, Hibernian Industrial Estate, Greenhills Road, Dublin 24, D24N673
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?