← Back to search

Unit 13, Hibernian Industrial Estate, Greenhills Road, Dublin 24

Declared Not Exempt

Planning application ED20/0011

Dublin - South Dublin County Council

Application Timeline

  1. Further information requested

    15 Jun 2020

  2. Application received

    1 Jul 2020

  3. Further information received

    1 Jul 2020

  4. Decision: Declared Not Exempt

    20 Jul 2020

  5. Decision due

    21 Jul 2020

Application Details

Location
Unit 13, Hibernian Industrial Estate, Greenhills Road, Dublin 24
Applicant
N/A
Application Type
Declaration of Exemption Sect. 5
Planning Authority
South Dublin County Council
Site Area
2346.97847668926 ha

Timeline

Registration Date
1 July 2020
Status
Officer Allocation
Decision
Declared Not Exempt
Decision Date
20 July 2020

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

33m
SD07A/0317Invalid - Site Notice1 May 2007

Retention of change of use from manufacturing unit to wholesale and distribution unit with ancillary office and trade counter.

12, Hibernian Industrial Estate, Greenhills Road, Tallaght, Dublin 24

33m
SD07A/0901Grant Permission for Retention13 Nov 2007

Retention of change of use from manufacturing unit to wholesale and distribution unit with ancillary office and trade counter.

Unit 12, Hibernian Industrial Estate, Greenhills Road, Tallaght, Dublin 24

84m
SD04A/0529Granted4 Oct 2004

Alterations to an existing industrial warehouse which is to include: new Brise Soleil Louvres measuring a total of 33sq.m to existing windows to north facade; two no. new canopies measuring a total of 59sq.m over two no. existing loading bays to east facade and associated rain water drainage; two no. new canopies over existing side door to warehouse and existing office entrance to north facade measuring a total of 7sq.m; new programmable electronic signage and new internally illuminated signage as well as single non-illuminated sign measuring a total of 22sq.m to north facade to incorporate single tube feature neon light to north facade; three no. alternative fabric banners measuring a total of 11sq.m suspended from three no. new flag poles; four no. new mounting posts with CCTV cameras; new perimeter fence to be built over existing walls to west, north and east boundaries to incorporate: new car entrance to north boundary with associated new access ramp measuring 48sq.m. with associated new sliding gate, two no. new sliding gates to two no. existing entrances to east boundary, new hinged access gate to replace existing pedestrian access gate to west boundary and removal of existing pallisade fence between west facade and west boundary.

No., 16/17, Hibernian Industrial Estate, Greenhills Road, Tallaght, Dublin 24

84m
SD04A/0642Granted24 Nov 2004

The development consists of the change of use of part of the existing ground floor office accommodation and secondary stores measuring approx. 80 m2 associated with the existing industrial warehouse building to form a retail unit related to the operation of the storage facility within the warehouse.

No. 16/17 Hibernian Industrial Estate, Greenhills Road, Tallaght, Dublin 24

84m
SD22A/0268Granted6 Oct 2022

Extension to the front and side of the existing storage warehouse building (314.00sqm) with ancillary office space and new exterior illuminated signage to front and side and ancillary site works.

17, Hibernian Estate, Tallaght, Dubin 24, D24 K163

91m
ED06/0038Declared Not Exempt11 Oct 2006

Change of use of premises from manufacturing (office furniture assembly) to wholesale and distribution with ancillary offices and trade counter (for building materials - plasterboard slabs etc).

Unit 2, Hibernian Industrial Estate, Greenhills Road, Tallaght, Dublin, 24

93m
SD19A/0161Granted10 May 2019

Subdivision of single light industrial/warehouse unit into three self-contained, light industrial/warehouse units; vehicular entrance on east elevation; all associated ancillary site works.

Serla House, Hibernian Industrial Estate, Greenhills Road, Tallaght, Dublin 24

107m
ED14/0029Declared Exempt12 Aug 2014

New 110kv cables to be connected to the existing building through new openings on the first floor. Supporting framework will carry the cables from the breakout point in the northern exterior wall into underground ducting within the ESB compound. These (exempted) cables will then continue underground to other ares within the Amazon complex.

Amazon Complex, Hibernian Insurance Industrial Estate, Greenhills Road, Tallaght, Dublin 24

111m
S99A/0080Granted19 Apr 1999

For two storey Showroom, Office and Warehouse extension to side of existing Eurohaul premises.

Eurohaul premises, Greenhills Road, Tallaght, Dublin 24.

114m
SD16A/0339Granted27 Sept 2016

Demolition of an existing link between warehouse/office Units14/15, dividing the connected units into two separate self-contained warehouse/office units, and to provide a new pedestrian entrance to the front of Unit 15.

Unit 14/15, Hibernian Industrial Estate, Greenhills Road, Dublin 24

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?