Lackanastooka Ballydesmond Co. Cork
CONDITIONALPlanning application 18/4451
Cork - Cork County Council
Proposed Development
Construct a 1,524sq.m dispatch yard storage building for the storage of finished products of windows and doors. Permission is also sought to replace the existing north facing dispatch yard blockwork boundary wall with a concrete panel and blockwork pillar type construction together with all ancillary services and associated site works
View the full application file on the council's planning portal →Application Timeline
Application received
22 Feb 2018
Decision due
18 Apr 2018
Decision: CONDITIONAL
18 Apr 2018
Grant issued
25 May 2018
Application Details
- Location
- Lackanastooka Ballydesmond Co. Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 22 February 2018
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 18 April 2018
- Grant Date
- 25 May 2018
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Construction of access tunnel under roadway at window and door manufacturing facility
LACKANASTOOKA, LACKANASTOOKA,
Construction of four storey office building comprising of reception, offices, file storage room and toilets on ground floor, canteen and toilets on first floor, open plan offices, storage room and toilets on second floor and open plan offices and file storage rooms on third floor
Munster Joinery Lacka Cross Lackanastooka Ballydesmond
2 no. wind turbines (80m hub height and 80m blade diameter) with overall height not exceeding 125m high, 2 no. transformers, site track and associated works
Lackanastooka Ballydesmond
Construction of standby diesel generator compound with switchroom at window and door manufacturing facility
Munster Joinery Lacka Cross Lackanastooka Ballydesmond
Alteration and extension of existing waste water treatment plant with buried discharge pipeline at window and door manufacturing facility
Munster Joinery Lacka Cross Lackanastooka Ballydesmond
Extension to the aluminium building for the purpose of increasing the production line capability
Munster Joinery Lacka Cross Lackanastooka Ballydesmond
Retention of an access road, associated retaining walls with a total area of 840sq.m and all associated site and ancillary works.
Lacka Cross Lackanastooka Ballydesmond Co. Cork
The demolition of an existing dwelling and the construction of an industrial production building (3157 sq.m) complete with canteen, toilet and first aid facilities, electrical switch room and office space, solar panels on the south-facing roof section, an adjacent concrete yard (970 sq.m), attenuation drainage system and landscaping works at the Gairdini facility. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with this application.
Lackanastooka Ballydesmond Co. Cork
A car parking facility complete with flood lighting, access road and new entrance adjacent to public road.
Munster Joinery Lacka Cross, Lackanastooka Ballydesmond Co. Cork
A car parking facility complete with flood lighting, access road and new entrance adjacent to public road.
Munster Joinery Lacka Cross Lackanastooka, Ballydesmond Co. Cork