← Back to search

Old Birr Road , Nenagh , Co. Tipperary

CONDITIONAL

Planning application 2334

Tipperary - Tipperary County Council

Proposed Development

domestic extension at rear of dwelling and PERMISSION to erect new domestic extension to same dwelling

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    13 Feb 2023

  2. Decision: CONDITIONAL

    29 Mar 2023

  3. Decision due

    9 Apr 2023

  4. Grant issued

    2 May 2023

Application Details

Location
Old Birr Road , Nenagh , Co. Tipperary
Applicant
N/A
Application Type
RETENTION
Planning Authority
Tipperary County Council
Site Area
0.015 ha

Timeline

Registration Date
13 February 2023
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
29 March 2023
Grant Date
2 May 2023
Permission Expires
1 May 2028

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

20m
2587CONDITIONAL26 May 2025

a) construction of a commercial storage yard; b) retention of associated boundary walls within the curtilage of said yard; c) retention of placement of a portable cabin within the yard; and d.) PERMISSION for future construction of an open roofed structure within the yard

Bulfin Road , Nenagh , Co Tipperary

42m
258CONDITIONAL22 Jan 2025

as-constructed single storey extension to the rear of Friary Ironworks

Unit 1 Riverstown Industrial Park , Old Birr Road , Nenagh Co. Tipperary

61m
21822N/A8 Jun 2021

construction of dry goods store and associated site works

Old Birr Road , Nenagh , Co Tipperary

72m
20625N/A18 Jun 2020

pedestrian access gate from site boundary onto Bulfin Road

No. 9 Derrylavin Heights , Nenagh , Co. Tipperary

73m
20716CONDITIONAL7 Jul 2020

for pedestrian access gate from site boundary at No 9 Derrylavin Heights onto Bulfin Road, Nenagh

No 9 Derrylavin Heights , Nenagh , Co Tipperary

76m
21949N/A1 Jul 2021

construction of dry goods store and associated site works

Old Birr Road , Nenagh , Co Tipperary

76m
18601090CONDITIONAL7 Sept 2018

existing building for commercial purposes

Old Birr Road , Nenagh , Co. Tipperary

118m
2460771N/A13 Sept 2024

the construction of a new commercial vehicle test centre with inspection pit, ancillary office, waiting area, toilets & connection to existing mains sewer & surface water services and all associated site works

Nenagh North , Nenagh , Co. Tipperary

129m
2460961N/A8 Nov 2024

an upgrade to the existing Nenagh wastewater treatment plant from its current design Population Equivalent (PE) of 12,000 to a PE plant of 22,000. The wastewater will be treated and discharged via an upgraded outfall pipe into the Nenagh river to the immediate east of the site. The proposed development will comprise of proposed construction of: dual inlet pumping station; storm overflow chamber complete with overflow screens; 2 no. storm tanks including storm return pumps and tank cleaning systems; preliminary treatment stream comprising: fine screens complete with screenings handling systems; grit removal system complete with fat, oil and grease removal; grit handling system and fat, oil and grease storage tank; sludge process stream comprising: sludge import station complete with ancillary equipment; waste activated sludge buffer tank complete with ancillary equipment; picket fence thickeners complete with ancillary equipment; thickened sludge tanks complete with transfer pumps; sludge dewatering system complete with outdoor sludge skips; polymer make-up and dosing plant; return liquors pumping station; sequencing batch reactor tanks and blowers with distribution chamber; ferric sulphate dosing plant; tertiary treatment disk filter and wastewater pumping station; 2 no. odour control units with additional passive odour units; new ESB MV substation complete with outdoor generator and bunded fuel storage tanks; new control panel kiosks; upgrade of outfall headwall to Nenagh river; site lighting; flood defence walls to existing buildings and flood compensation areas; revised site entrance including lay-by area and palisade fencing and flow measurement and sampling chambers. Proposed re-purposing of existing structures as follows: conversion of existing picket fence thickener to a sludge import pumping station; conversion of existing final settlement tank to a final effluent buffer tank; conversion of existing final settlement tank to a surface water attenuation tank; diversion of existing northern catchment gravity main to proposed inlet pumping station and diversion of existing southern catchment rising main to proposed inlet pumping station. Demolition of the following: existing (northern and southern) oxidation ditches to be demolished and partially filled in; existing return activated sludge lifting wheel arrangement; existing waste activated system pumping station; existing belt thickeners and poly plant; existing inlet works; existing flow splitti

The existing Wastewater Treatment Plant , Bulfin Road , Nenagh in the townland of Nenagh North

129m
2461086CONDITIONAL12 Dec 2024

an upgrade the existing Nenagh Wastewater Treatment Plant from its current design Population Equivalent (PE) of 12,000 to a PE plant of 22,000. The wastewater will be treated and discharged via an upgraded outfall pipe into the Nenagh River to the immediate east of the site. The proposed development will comprise of: Proposed construction of: • Dual inlet pumping station • Storm overflow chamber complete with overflow screens • 2 No. storm tanks including storm return pumps and tank cleaning systems • Preliminary Treatment Stream comprising: • Fine Screens complete with screenings handling systems • Grit Removal system complete with fat, oil and grease removal • Grit Handling system and fat, oil and grease storage tank • Sludge Process Stream comprising: • Sludge Import Station complete with ancillary equipment • Waste Activated Sludge Buffer Tank complete with ancillary equipment • Picket Fence Thickeners complete with ancillary equipment • Thickened Sludge Tanks complete with transfer pumps • Sludge Dewatering system complete with outdoor sludge skips • Polymer make-up and dosing plant • Return liquors pumping station • Sequencing Batch Reactor tanks and blowers with distribution chamber • Ferric sulphate dosing plant • Tertiary Treatment Disk Filter and wastewater pumping station • 2 No. Odour Control Units with additional passive odour units • New ESB MV substation complete with outdoor generator and bunded fuel storage tanks • New control panel kiosks • Upgrade of outfall headwall to Nenagh River • Site lighting • Flood defence walls to existing buildings and Flood Compensation Areas • Revised site entrance including layby area and palisade fencing • Flow measurement and sampling chambers Proposed repurposing of existing structures as follows: • Conversion of existing Picket Fence Thickener to a sludge import pumping station. • Conversion of existing Final Settlement Tank to a final effluent buffer tank. • Conversion of existing Final Settlement Tank to a surface water attenuation tank. • Diversion of existing Northern Catchment gravity main to proposed inlet pumping station. • Diversion of existing Southern Catchment rising main to proposed inlet pumping station. Demolition of the following: • Existing (northern and southern) oxidation ditches to be demolished and partially filled in. • Existing Return Activated Sludge lifting wheel arrangement • Existing Waste Activated System pumping station • Existing belt thicken

The existing Wastewater Treatment Plant , Bulfin Road , Nenagh in the townland of Nenagh North

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?