Unit 1 Riverstown Industrial Park , Old Birr Road , Nenagh Co. Tipperary
CONDITIONALPlanning application 258
Tipperary - Tipperary County Council
Proposed Development
as-constructed single storey extension to the rear of Friary Ironworks
View the full application file on the council's planning portal →Application Timeline
Application received
22 Jan 2025
Decision: CONDITIONAL
11 Mar 2025
Decision due
18 Mar 2025
Grant issued
14 Apr 2025
Application Details
- Location
- Unit 1 Riverstown Industrial Park , Old Birr Road , Nenagh Co. Tipperary
- Applicant
- N/A
- Application Type
- RETENTION
- Planning Authority
- Tipperary County Council
Timeline
- Registration Date
- 22 January 2025
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 11 March 2025
- Grant Date
- 14 April 2025
- Permission Expires
- 13 April 2030
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
domestic extension at rear of dwelling and PERMISSION to erect new domestic extension to same dwelling
Old Birr Road , Nenagh , Co. Tipperary
a) construction of a commercial storage yard; b) retention of associated boundary walls within the curtilage of said yard; c) retention of placement of a portable cabin within the yard; and d.) PERMISSION for future construction of an open roofed structure within the yard
Bulfin Road , Nenagh , Co Tipperary
construction of dry goods store and associated site works
Old Birr Road , Nenagh , Co Tipperary
existing building for commercial purposes
Old Birr Road , Nenagh , Co. Tipperary
construction of dry goods store and associated site works
Old Birr Road , Nenagh , Co Tipperary
for pedestrian access gate from site boundary at No 9 Derrylavin Heights onto Bulfin Road, Nenagh
No 9 Derrylavin Heights , Nenagh , Co Tipperary
pedestrian access gate from site boundary onto Bulfin Road
No. 9 Derrylavin Heights , Nenagh , Co. Tipperary
an upgrade to the existing Nenagh wastewater treatment plant from its current design Population Equivalent (PE) of 12,000 to a PE plant of 22,000. The wastewater will be treated and discharged via an upgraded outfall pipe into the Nenagh river to the immediate east of the site. The proposed development will comprise of proposed construction of: dual inlet pumping station; storm overflow chamber complete with overflow screens; 2 no. storm tanks including storm return pumps and tank cleaning systems; preliminary treatment stream comprising: fine screens complete with screenings handling systems; grit removal system complete with fat, oil and grease removal; grit handling system and fat, oil and grease storage tank; sludge process stream comprising: sludge import station complete with ancillary equipment; waste activated sludge buffer tank complete with ancillary equipment; picket fence thickeners complete with ancillary equipment; thickened sludge tanks complete with transfer pumps; sludge dewatering system complete with outdoor sludge skips; polymer make-up and dosing plant; return liquors pumping station; sequencing batch reactor tanks and blowers with distribution chamber; ferric sulphate dosing plant; tertiary treatment disk filter and wastewater pumping station; 2 no. odour control units with additional passive odour units; new ESB MV substation complete with outdoor generator and bunded fuel storage tanks; new control panel kiosks; upgrade of outfall headwall to Nenagh river; site lighting; flood defence walls to existing buildings and flood compensation areas; revised site entrance including lay-by area and palisade fencing and flow measurement and sampling chambers. Proposed re-purposing of existing structures as follows: conversion of existing picket fence thickener to a sludge import pumping station; conversion of existing final settlement tank to a final effluent buffer tank; conversion of existing final settlement tank to a surface water attenuation tank; diversion of existing northern catchment gravity main to proposed inlet pumping station and diversion of existing southern catchment rising main to proposed inlet pumping station. Demolition of the following: existing (northern and southern) oxidation ditches to be demolished and partially filled in; existing return activated sludge lifting wheel arrangement; existing waste activated system pumping station; existing belt thickeners and poly plant; existing inlet works; existing flow splitti
The existing Wastewater Treatment Plant , Bulfin Road , Nenagh in the townland of Nenagh North
an upgrade the existing Nenagh Wastewater Treatment Plant from its current design Population Equivalent (PE) of 12,000 to a PE plant of 22,000. The wastewater will be treated and discharged via an upgraded outfall pipe into the Nenagh River to the immediate east of the site. The proposed development will comprise of: Proposed construction of: • Dual inlet pumping station • Storm overflow chamber complete with overflow screens • 2 No. storm tanks including storm return pumps and tank cleaning systems • Preliminary Treatment Stream comprising: • Fine Screens complete with screenings handling systems • Grit Removal system complete with fat, oil and grease removal • Grit Handling system and fat, oil and grease storage tank • Sludge Process Stream comprising: • Sludge Import Station complete with ancillary equipment • Waste Activated Sludge Buffer Tank complete with ancillary equipment • Picket Fence Thickeners complete with ancillary equipment • Thickened Sludge Tanks complete with transfer pumps • Sludge Dewatering system complete with outdoor sludge skips • Polymer make-up and dosing plant • Return liquors pumping station • Sequencing Batch Reactor tanks and blowers with distribution chamber • Ferric sulphate dosing plant • Tertiary Treatment Disk Filter and wastewater pumping station • 2 No. Odour Control Units with additional passive odour units • New ESB MV substation complete with outdoor generator and bunded fuel storage tanks • New control panel kiosks • Upgrade of outfall headwall to Nenagh River • Site lighting • Flood defence walls to existing buildings and Flood Compensation Areas • Revised site entrance including layby area and palisade fencing • Flow measurement and sampling chambers Proposed repurposing of existing structures as follows: • Conversion of existing Picket Fence Thickener to a sludge import pumping station. • Conversion of existing Final Settlement Tank to a final effluent buffer tank. • Conversion of existing Final Settlement Tank to a surface water attenuation tank. • Diversion of existing Northern Catchment gravity main to proposed inlet pumping station. • Diversion of existing Southern Catchment rising main to proposed inlet pumping station. Demolition of the following: • Existing (northern and southern) oxidation ditches to be demolished and partially filled in. • Existing Return Activated Sludge lifting wheel arrangement • Existing Waste Activated System pumping station • Existing belt thicken
The existing Wastewater Treatment Plant , Bulfin Road , Nenagh in the townland of Nenagh North
install 35kW of ground mounted Solar PV Panels and all associated works
Nenagh Sewage Treatment Plant , Bulfin Road , Nenagh
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?